

CONSTRUCTION UPDATES
WEEK OF APRIL 19, 2021
Monday, April 19, 2021
-
R.W. Dunteman Company placed and compacted capping on the new Weiland Road east of Buffalo Grove Road, broke pavement on southbound Weiland Road south of Lake Cook Road and graded sidewalk on eastbound Lake Cook Road
-
Areatha poured and placed protective blankets on the southwest section of the west abutment on Weiland Road Bridge
-
Trine installed storm sewer reinforced concrete pipes and structures on Buffalo Grove Road north of Lake Cook Road and installed the underdrain by Buffalo Grove Road and Weiland Road
-
Home Towne installed a unit duct for street lighting on northbound IL-83
-
Quality saw cut pavement on Weiland Road north of Lake Cook Road and on IL-83 south of Lake Cook Road

Tuesday, April 20, 2021
-
R.W. Dunteman Company removed raised reflectors on the asphalt pavement from IL-83 north of Lake Cook Road
-
Areatha poured and placed protective blankets on the northwest section of the west abutment on Weiland Road Bridge
-
Trine filled an abandoned water main on Lake Cook Road, west of IL-83
-
Home Towne installed an electric service box on the existing wood pole on the southwest side of Lake Cook Road and Buffalo Grove Road

Wednesday, April 21, 2021

-
R.W. Dunteman Company removed pavement on southbound IL-83 south of Lake Cook Road
-
Areatha poured and placed protective blankets on the parapet wall on the northeast wing wall of Buffalo Grove Road Bridge
-
Trine installed the storm sewer reinforced concrete pipes and structures on St. Mary Street west of Buffalo Grove Road Road
-
Home Towne excavated and installed casing, installed conduits and framed handholes for traffic signals by IL-83 and Weiland Road
Thursday, April 22, 2021

-
R.W. Dunteman Company excavated, cut, and rolled subgrade on southbound Weiland south of Lake Cook Road
-
Areatha stripped forms at the northwest abutment of Weiland Road Bridge
-
Trine installed proposed storm sewer reinforced concrete pipes and a water main on St. Mary Street west of Buffalo Grove Road
-
Home Towne installed conduits and framed HH for traffic signals by IL-83 and Weiland Road
Friday, April 23, 2021

-
R.W. Dunteman Company framed, graded and prepared concrete pavement and the median on Weiland Road south of Lake Cook Road
-
Areatha stripped forms for the parapet pour and under deck area and demobilized materials to the yard
-
Trine installed reinforced concrete pipes and structures on St. Mary Street west of Buffalo Grove Road
-
TCP switched maintenance of traffic into stage 3 on Lake Cook Road Weiland Road to the east limit of the project area
-
Ruizscape placed ditch checks behind wall F & E along Buffalo Creek and placed a temporary fence along northbound Weiland Road north of Lake Cook Road
Saturday, April 24, 2021

-
R.W. Dunteman Company pumped out water at Buffalo Creek by Weiland Road Bridge and placed aggregate subgrade on Weiland Road by Lake Cook Road
-
Home Towne poured light pole foundations, double handhole, and controller foundations along Lake Cook Road