Monday, April 26, 2021

  • R.W. Dunteman Company installed embankment behind the east abutment on Weiland Road Bridge, excavated earth, and removed unsuitable material on southbound IL-83 south of Lake Cook Road

  • Areatha built overhang brackets and decking materials for Weiland Road Bridge

  • Trine installed underdrain, removed existing storm sewer reinforced concrete pipes on southbound Weiland Rodd south of Lake Cook Road

  • Home Towne installed conduit for traffic signals on northbound IL-83 by Jewel

  • Clausen prepared diaphragms for Weiland Road beam erection

  • Industrial Fence Inc.  relocated temporary attenuators on Buffalo Grove Road Bridge and at the Lake Cook Road and Buffalo Grove Road intersection for the maintenance of traffic stage 5 switch

  • Trafic Services Inc. switched traffic to the maintenance of traffic stage 5 on Buffalo Grove Road

  • Maintenance Coating Co. removed temporary concrete barrier walls on Buffalo Grove Road Bridge and at the Lake Cook Road and Buffalo Grove Road intersection for the maintenance of traffic stage 5 switch

RWD_WeilandRdTurnLane_04262021.jpg

Tuesday, April 27, 2021

  • R.W. Dunteman Company excavated unsuitable material and placed embankment on the east abutment of Weiland Road Bridge

  • Areatha removed existing railing, installed temporary wooden rails, laid out saw cuts on the west side of Buffalo Grove Road Bridge

  • Home Towne installed conduit for traffic signals by Lake Cook Road and Weiland Road and shifted traffic signal heads on Lake Cook Road and Lexington Drive for the maintenance of traffic switch

  • Trafic Services Inc. switched to traffic to the maintenance of traffic Stage 4B on Lexington Drive and place barricades on Buffalo Grove Road Bridge for safety

  • Antigo broke existing concrete pavement on southbound Weiland Road north of Lake Cook Road

  • Quality saw cut existing pavement on eastbound Lake Cook Road between Walmart and the project east limit and on southbound Buffalo Grove Road north of Lake Cook Road

20210427_180207.jpg

Wednesday, April 28, 2021

Trine_EBLCRSSRCPReplacement_04282021.jpg
  • R.W. Dunteman Company removed pavement, placed aggregate subgrade and capping on southbound Weiland Road south of Lake Cook Road, removed embankment behind the east. abutment on Weiland Road Bridge, poured concrete pavement (on eastbound Lake Cook Road by the Bank of America, on northbound IL-83 by Jewel, on eastbound Lake Cook Road by Weiland Road, on eastbound Lake Cook Road), and poured concrete pavement and curb and gutter by the northbound Weiland Road extension

  • Areatha removed existing asphalt surface from existing bridge deck on Buffalo Grove Road Bridge

  • Trine installed proposed storm sewer reinforced concrete pipes and structures on eastbound Lake Cook Road east of Walmart

  • Home Towne conducted general site cleanup

Thursday, April 29, 2021

RWD_Cap&Frame&GradeSBWeilandRd_04292021.
  • R.W. Dunteman Company graded subgrade capping and framed southbound Weiland Road and place grindings on the southwest corner of Lake Cook Road and IL-83

  • Areatha removed the existing asphalt surface from the deck and demolished the existing southwest asphalt on Buffalo Grove Road Bridge

  • Trine removed and replaced the existing storm sewer reinforced concrete pipes and installed storm sewer structures on eastbound Lake Cook Road east of Walmart

  • Ruizscape cleaned the front face and placed rip rap stone on the east and west abutments of the Weiland Road Bridge

  • Quality saw cut the sidewalk on the Buffalo Grove Road Bridge deck

Friday, April 30, 2021

Clausen_WeilandRdBridgePCCBeamErection2_
  • R.W. Dunteman Company poured concrete pavement on southbound Weiland Road between IL-83 and Lake Cook Road

  • Areatha demolished the existing southwest parapet on Buffalo Grove Road Bridge and installed protective shielding between the beams on Weiland Road Bridge

  • Trine removed and replaced existing storm sewer reinforced concrete pipes and installed storm sewer structures on eastbound Lake Cook Road east of Walmart

  • Home Towne adjusted detector loops along the Lake Cook Road intersections

  • Clausen installed prestressed concrete pavement beams and diaphragms on Weiland Road Bridge

Saturday, May 1, 2021

  • Areatha installed protective shielding between beams and bridge deck hangers on Weiland Road Bridge