  • R.W. Dunteman Company removed the existing concrete pavement, curb and gutter and sidewalk on southbound Weiland Road north of Lake Cook Road and continued to frame and grade the curb and gutter for the driveway on southbound Weiland Road

  • Areatha continued the removal of the existing parapet wall on the west side Buffalo Grove Road Bridge deck and continued to frame the Weiland Road Bridge deck for the upcoming deck pour

  • Trine installed a sanitary force main for the Bank of America property at the southeast corner of IL-83 and Lake Cook Road

  • Clausen finished the installation of beam diaphragms on the Weiland Road Bridge

Areatha_BGRdBridgeDeckDemo_05032021.jpg

Tuesday, May 4, 2021

  • R.W. Dunteman poured concrete pavement, curb and gutter driveways and temporary pavement on southbound Weiland Road south of Lake Cook Road and began excavation and preparation of subgrade along the north end of Weiland Road between Lake Cook Road and Armstrong Drive

  • Areatha continued removal of the existing parapet wall on the west side Buffalo Grove Road Bridge deck and continued to frame the Weiland Road Bridge deck for the upcoming deck pour

  • Quality Saw saw cut existing the Buffalo Grove Road Bridge deck

  • Trine continued the removal and replacement of the storm sewer pipe and structures along eastbound Lake Cook Road east of the Target and Walmart intersection to Lexington Drive

  • Ruizscape installed temporary erosion control measures along Buffalo Creek and placed inlet filters along the Lake Cook Road storm sewer structures

RWD_SBWeilandC&GDrivewayPour_05042021.jp

Wednesday, May 5, 2021

RWD_SB83Frame&Grade_05052021.jpg
  • R.W. Dunteman continued to excavate and prepare for subgrade on southbound Weiland Road north of Lake Cook Road, prepared for the placement of temporary pavement along Lake Cook Road and framed and graded southbound of IL-83 for the upcoming pavement pour

  • Quality saw cut the existing deck on the west side of Buffalo Grove Road Bridge

  • Trine continued the removal and replacement of the storm sewer pipe and structures along eastbound Lake Cook Road east of the Target and Walmart intersection to Lexington Drive

  • Areatha continued the removal of the existing bridge deck on the west side of Buffalo Grove Road Bridge and continued to frame the Weiland Road Bridge deck for the upcoming deck pour

Thursday, May 6, 2021

Trine_WBLCRSSStructureInstallation_05052
  • AC Iron onsite to tie rebar at Weiland Road Bridge for the east abutment diaphragm

  • Quality saw cut the existing deck on the west side of Buffalo Grove Road Bridge

  • Trine continued the removal and replacement of the storm sewer pipe and structures along eastbound Lake Cook Road east of the Target and Walmart intersection to Lexington Drive

  • Areatha continued the removal of the existing bridge deck on the west side of Buffalo Grove Road Bridge and continued to frame Weiland Road Bridge deck for the upcoming deck pour

Friday, May 7, 2021

RWD_SBWeilandSWRem_05072021.jpg
  • R.W. Dunteman continued the removal of existing pavement and curb and gutter along Weiland Road north of Lake Cook Road, poured concrete pavement on IL-83 south of Lake Cook Road and poured temporary pavement on Lake Cook Road for the barrier wall placement

  • AC Iron onsite to tie rebar for the Weiland Road bridge deck

  • Trine continue the removal and replacement of the storm sewer pipe and structures along eastbound Lake Cook Road east of Target and Walmart intersection to Lexington Drive

  • Areatha continued the removal of the existing bridge deck on the west side of Buffalo Grove Road Bridge continued to frame the Weiland Road Bridge deck for the upcoming deck pour

Saturday, May 8, 2021

  • Areatha continued to frame the Weiland Road Bridge deck for the upcoming deck pour