CONSTRUCTION UPDATES
WEEK OF MAY 31, 2021
Tuesday, June 1, 2021
-
R.W. Dunteman Company excavated and prepared subgrade on southbound Buffalo Grove Road north of Lake Cook Road and placed capping material in the preparation of pavement on southbound IL-83 by the Jewel intersection
-
Areatha poured the approach slab footings for the Weiland Road Bridge and continue to drill and set soldier piles for retaining Wall C
-
Trine finished the installation of the 3" sanitary sewer for the Bank of America and continued to install storm sewer pipe and structures along westbound Lake Cook Road west of Buffalo Grove Road
-
Home Towne drilled and placed rebar cage for light pole foundations on southbound IL-83

Wednesday, June 2, 2021

-
R.W. Dunteman Company prepared subgrade on southbound Buffalo Grove Road north of Lake Cook Road and began excavations along eastbound Lake Cook Road just east of the Target and Walmart intersection
-
Areatha poured the remaining sections of the approach slab footings on the Weiland Road Bridge and continued to drill and set soldier piles for retaining Wall C
-
Trine continued to remove and replace storm sewer pipe and structures along westbound Lake Cook Road west of Buffalo Grove Road and removed and installed 8” sanitary sewer along westbound Lake Cook Road by the Jewel shopping center
-
Home Towne framed and poured light pole foundations on southbound IL-83 and Weiland Road and began the installation of the temporary traffic signals at Buffalo Grove Road and Weiland Road for the upcoming traffic configuration switch
-
AC Iron tied rebar for the approach footing on Weiland Road Bridge
-
Industrial Fence Inc onsite removed and relocated attenuators on eastbound Lake Cook Road by Buffalo Grove Road Bridge and on southbound IL-83
-
Maintenance Coating Co relocated the temporary concrete barrier wall on Lake Cook Road by Buffalo Grove Road
Thursday, June 3, 2021

-
R.W. Dunteman Company placed aggregate subgrade and the pipe underdrain along southbound Buffalo Grove Road north of Lake Cook Road and continued to excavate and prepare subgrade along eastbound Lake Cook Road east of the Target and Walmart intersection
-
Areatha continued to drill and set soldier piles for retaining Wall C and backfilled behind the Weiland Road Bridge east and west abutments
-
Trine installed pipe underdrain on southbound IL-83 north of Lake Cook Road and removed and replaced storm sewer pipe and structures along westbound Lake Cook Road west of Buffalo Grove Road
-
Home Towne installed conduits for traffic signals on southbound Buffalo Grove Road and continued installing the temporary traffic signals at Buffalo Grove Road and Weiland Road
Friday, June 4, 2021

-
R.W. Dunteman Company continued to excavate and prepare the subgrade on eastbound Lake Cook Road east of the Target and Walmart intersection and placed aggregate subgrade on southbound IL-83 north of Lake Cook Road
-
Areatha continued to drill and set soldier piles for retaining Wall C and backfilled behind the Weiland Road Bridge east and west abutments
-
Trine continued to remove and replace storm sewer pipe and structures along westbound Lake Cook Road west of Buffalo Grove Road and finished the remaining work with the sanitary sewer along westbound Lake Cook Road by the Jewel shopping center
-
Home Towne installed conduits under Weiland Road Bridge, excavated for a traffic signal foundation at the southeast corner of Weiland Road and IL-83, and continued to set up the temporary traffic signals at Buffalo Grove Road and Weiland Road
Saturday, June 5, 2021

-
Areatha prepared forms for the approach slabs on the east and west side of Weiland Road bridge