CONSTRUCTION UPDATES
WEEK OF JUNE 7, 2021
Monday, June 7, 2021
-
R.W. Dunteman Company excavated and prepared subgrade on eastbound Lake Cook Road from the Target and Walmart intersection to Lexington Drive, started placement of aggregate subgrade, continued to remove existing pavement on eastbound Lake Cook Road from Lexington Drive to Hastings Lane, fine graded the aggregate subgrade on Buffalo Grove Road, and IL-83 north of Lake Cook Road in preparation for the concrete pavement
-
Trine cut the existing pavement and started to install 8" and 16" water main along Buffalo Grove Road by St Mary’s Parkway and continued to remove and install storm sewer pipes and structures along westbound Lake Cook Road just west of Buffalo Grove Road
-
Areatha continued to drill and set soldier piles for retaining Wall C
-
Home Towne continued to install temporary traffic signals at the Weiland Road and Buffalo Grove Road intersection and continued to install new conduits on the east and west abutments of the Weiland Road Bridge

Tuesday, June 8, 2021

-
R.W. Dunteman Company excavated and prepared subgrade on eastbound Lake Cook Road from the Target and Walmart intersection to Lexington Drive, continued to remove existing pavement on eastbound Lake Cook Road from Lexington Drive to Hastings Lane, and graded and prepared forms for the concrete pavement on southbound IL-83 north of Lake Cook Road
-
Trine continued to install 8" & 16" water main along Buffalo Grove Road by St Mary’s Parkway and removed existing storm sewer pipes and structures along westbound Lake Cook Road just west of Buffalo Grove Road
-
Areatha continued to drill and set soldier piles for retaining Wall C
-
Home Towne bore new conduit across IL-83 and by Weiland Road for the new traffic signals and drilled a new traffic signal foundation at the northwest corner of IL-83 and Weiland Road
Wednesday, June 9, 2021

-
R.W. Dunteman Company excavated and prepared subgrade on eastbound Lake Cook Road from the Target and Walmart intersection to Lexington Drive, continued to remove existing pavement on eastbound Lake Cook Road from Lexington Drive to Hastings Lane, and graded and prepared forms for the concrete pavement on southbound IL-83 north of Lake Cook Road
-
Trine continued to install 8" & 16" water main along Buffalo Grove by St Mary’s Parkway and continued to install storm sewer pipes and structures along westbound Lake Cook Road just west of IL-83
-
Areatha continued to drill and set soldier piles for retaining Wall C and prepared for approach slab construction on Weiland Road Bridge
-
Home Towne installed traffic signal foundations, handholes, and bore conduits for new traffic signals on Weiland Road by IL-83
-
AC Iron onsite to tie rebar for thr west approach slab on Weiland Road Bridge
Thursday, June 10, 2021

-
R.W. Dunteman Company continued to remove existing pavement and prepared subgrade between Lexington Drive and Hastings Lane, prepared forms along southbound Buffalo Grove Road for the upcoming pavement pour, and poured concrete pavement for lanes 1 and 2 on southbound IL-83 north of Lake Cook Road
-
Trine completed the 20” water main connection along Weiland Road and continued to install storm sewer pipes and structures along westbound Lake Cook Road just west of IL-83
-
Areatha continued to drill and set soldier piles for retaining Wall C and prepared for the approach slab construction on Weiland Road Bridge
-
AC Iron to tie rebar for the east approach slab on Weiland Road Bridge
-
Trafic Services Inc placed traffic into the new traffic configuration on Buffalo Grove Road south of Lake Cook Road
Friday, June 11, 2021

-
R.W. Dunteman Company removed the existing pavement at the Walmart entrance, continued to place aggregate subgrade along eastbound Lake Cook Road between Walmart and Lexington Drive, continued to excavate and prepare the subgrade between Lexington Drive and Hastings Lane, and poured concrete pavement for lane 1 and 2 on southbound Buffalo Grove Road north of Lake Cook Road
-
Trine continued to install storm sewer pipes and structures along westbound Lake Cook Road just west of IL-83
-
Areatha poured half of the east and west approach slabs on Weiland Road Bridge and continued to install lagging boards between the retaining Wall C soldier piles
-
AC Iron assisted with the approach slab pour on Weiland Road Bridge
Saturday, June 12, 2021
-
Areatha continued to frame the east sleeper slab and south parapet wall on Weiland Road Bridge