top of page

CONSTRUCTION UPDATES

JULY 14 - JULY 16, 2021

Wednesday, July 14, 2021

  • R.W. Dunteman Company framed and poured curb and gutter on southbound Buffalo Grove Road north of Lake Cook Road

  • Areatha framed the north parapet wall and stripped forms from the south parapet wall on Weiland Road Bridge

RWD 07142021.jpg

Thursday, July 15, 2021

Areatha Grooving 07152021.jpeg
  • Trine mobilized equipment to the job site by Weiland Road and IL-83

  • Areatha completed framing the north parapet wall on Weiland Road Bridge and continued to install the wall drain on retaining Wall C

  • Quality Saw onsite grooved the Weiland Road Bridge deck and approach slabs

Friday, July 16, 2021

Trine Storm Sewer 07162021.jpeg
  • Trine continued the installation of storm sewer pipe and structures along westbound Lake Cook Road east of IL-83

  • Areatha stripped forms from the parapet wall on Weiland Road Bridge and cut soldier piles to correct the elevation for retaining Wall C

  • R.W. Dunteman Company removed and framed curb and gutter on southbound Weiland Road north of Lake Cook Road and worked on framing for the concrete pavement on Weiland Road between the Weiland Road Bridge and IL-83 

bottom of page