CONSTRUCTION UPDATES
WEEK OF JULY 19, 2021
Monday, July 19, 2021
-
R.W. Dunteman Company poured the north connector pavement at the Weiland Road Bridge and poured concrete pavement on IL-83 by Weiland Road Bridge, poured curb and gutter on southbound IL-83 and on southbound Buffalo Grove Road north of Lake Cook Road. R.W. Dunteman Company placed aggregate base course on driveways along southbound IL-83 and southbound Buffalo Grove Road in preparation for asphalt placement and worked on excavating the topsoil at the northwest corner of the Buffalo Grove Road Bridge
-
Areatha excavated for the retaining Wall C facing wall and shear stud installation and continued to remove forms and decking material from the Weiland Road Bridge
-
Trine installed an additional 5' diameter manhole for the unknown Wheeling storm sewer pipe along eastbound Lake Cook Road by Hastings Lane
-
AC Iron laid out rebar for retaining Wall C

Tuesday, July 20, 2021

-
R.W. Dunteman Company framed and poured concrete for temporary sidewalk and curb and gutter on the southwest corner of Lake Cook Road and IL-83 and poured curb and gutter on southbound Weiland Road and southbound Buffalo Grove Road north of Lake Cook Road
-
Areatha drove sheet piles for the cofferdam located at the northwest corner of the Buffalo Grove Road bridge and continued to remove forms and decking material from the Weiland Road Bridge
-
Trine continued the installation and removal of storm sewer pipe and structures along westbound Lake Cook Road between Weiland and IL-83
-
AC Iron installed shear studs on the soldier piles and installed the facing wall rebar for retaining Wall C
Wednesday, July 21, 2021

-
R.W. Dunteman Company placed asphalt on southbound IL-83 and southbound Buffalo Grove Road driveways and continued to excavate and prepare subgrade along westbound Lake Cook Road west of the Buffalo Grove Road intersection
-
Areatha continued to drive sheet piles for cofferdam on the northwest corner of the Buffalo Grove Road Bridge, continued to remove forms and decking material from the Weiland Road Bridge, and sprayed a protective coat on the Weiland Road Bridge deck and parapet walls
-
Trine installed pipe underdrain by Weiland Road Bridge and by the northwest corner of Lake Cook Road and Weiland Road
-
AC Iron continued to install shear studs on the soldier piles and install the facing wall rebar for retaining Wall C
Thursday, July 22, 2021

-
R.W. Dunteman Company continue to prepare subgrade and started the placement of aggregate subgrade along westbound Lake Cook Road west of the Buffalo Grove Road intersection, framed pavement between the Weiland Road Bridge and IL-83, and placed aggregate base course in preparation for sidewalk placement along southbound IL-83
-
Areatha continued to drive sheet piles for the cofferdam on the northwest corner of the Buffalo Grove Road Bridge and worked on framing the facing wall on retaining Wall C
-
Trine continued the installation and removal of storm sewer pipe and structures along westbound Lake Cook Road between Weiland and IL-83
-
AC Iron continued to tie rebar for retaining Wall C
-
Industrial Fence Inc removed the existing handrail along westbound Lake Cook Road by St Mary’s School and removed the guardrail south of Buffalo Grove Road Bridge
Friday, July 23, 2021

-
R.W. Dunteman Company poured concrete pavement between the Weiland Road Bridge and IL-83, poured concrete pavement and sidewalk along southbound IL-83, and prepared subgrade and place aggregate subgrade along westbound Lake Cook Road west Buffalo Grove Road
-
Areatha demolished the existing northwest wing wall on Buffalo Grove Road bridge and continued to frame the facing wall on retaining Wall C
-
Trine continued the installation and removal of storm sewer pipe and structures along westbound Lake Cook Road between Weiland and IL-83
-
Home Towne onsite to install conduits under driveways along southbound Weiland Road north of Lake Cook Road and westbound Lake Cook Road west of Buffalo Grove Road
Saturday, July 24, 2021

-
Areatha continued to frame the facing wall on retaining Wall C