Monday, July 26, 2021
-
R.W. Dunteman Company poured concrete pavement on Weiland Road by IL-83, poured the median and curb and gutter on Weiland Road between IL-83 and Buffalo Grove Road, fine graded the aggregate subgrade along eastbound Lake Cook Road from the Target and Walmart intersection to Hastings Lane, prepared subgrade and placed aggregate subgrade along westbound Lake Cook Road from Raupp Boulevard to Buffalo Grove Road, and removed the existing pavement along westbound Lake Cook Road between Buffalo Grove Road and IL-83
-
Trine installed storm sewer pipe and structures along westbound Lake Cook Road west of Weiland Road and mobilized a second crew to start on water main connections on Buffalo Grove Road
-
Areatha continued to frame Retaining Wall C
-
Home Towne installed conduits for traffic signals on eastbound Lake Cook Road by the Target and Walmart intersection

Tuesday, July 27, 2021

-
R.W. Dunteman Company set up the slip form and tining machine in preparation of the concrete pavement pour along eastbound Lake Cook Road, continued to prepare the subgrade and placed aggregate subgrade along westbound Lake Cook Road from Raupp Boulevard to Buffalo Grove Road, and removed the existing pavement along westbound Lake Cook Road between Buffalo Grove Road and IL-83
-
Trine adjusted and set frames on storm sewer structures along eastbound Lake Cook Road and installed water service connections to residents along St Mary’s Parkway
-
Areatha broke down the existing north abutment and the northwest wing wall on the Buffalo Grove Road Bridge
Wednesday, July 28, 2021

-
R.W. Dunteman Company slip formed the concrete pavement along eastbound Lake Cook Road from the Target and Walmart intersection to Hastings Lane
-
Trine installed 2” copper service to the Buffalo Creek apartments along St Mary’s Parkway and continued to remove and replace storm sewer pipe and structures along westbound Lake Cook Road between IL-83 and Weiland Road
-
Areatha excavated for the cofferdam installation on the northwest wing wall of Buffalo Grove Road Bridge and stripped and relocated forms at Retaining Wall C
-
Home Towne installed conduits for traffic signals and street lighting on southbound IL-83 by Buffalo Gorve Town Center and drilled and installed rebar cage for light pole foundations on southbound IL-83 north of Lake Cook Road
Thursday, July 29, 2021

-
R.W. Dunteman Company poured concrete pavement on southbound IL-83 by the Jewel and Towne Center intersection, westbound Lake Cook Road at the northwest corner of IL-83 and Lake Cook Road, poured the sidewalk along southbound IL-83 north of Lake Cook Road, excavated along westbound Lake Cook Road between IL-83 and Buffalo Grove Road, and remove pavement from IL-83 to Weiland Road
-
Trine continued to remove existing storm sewer pipe and structures along westbound Lake Cook Road east of IL-83 and prepared for the upcoming water main connections along Buffalo Grove Road
-
Areatha continued to frame the facing wall for retaining Wall C
-
Home Towne drilled and installed rebar cage for light pole foundations on southbound IL-83 north of Lake Cook Road
Friday, July 30, 2021

-
R.W. Dunteman Company poured concrete pavement on eastbound Lake Cook Road by Lexington Drive and by the Walmart entrance, excavated along westbound Lake Cook Road between IL-83 and Buffalo Grove Road, and removed pavement from IL-83 to Weiland Road
-
Areatha continued to frame the facing wall for Retaining Wall C
-
Trine filled the abandoned water main and removed abandoned valve vaults on westboudnLake Cook Road west of Weiland Road amd prepared for water main connections on Buffalo Grove Road
Saturday, July 31, 2021

-
Areatha continued to frame the facing wall for retaining Wall C
-
Home Towne installed conduits for street lighting and traffic signals on westbound Lake Cook Road, southbound IL-83 by the Shell driveway, and westbound Lake Cook Road by the Walgreen driveway