Monday, August 9, 2021
-
R.W. Dunteman Company placed aggregate subbase on the eastbound Lake Cook Road Walmart truck entrance and removed existing pavement, and prepared subgrade at the northeast corner of Lake Cook Road and IL-83
-
Areatha stripped forms from retaining Wall C and continued to excavate the cofferdam for the Buffalo Grove Road Bridge widening
-
Home Towne drilled for light pole foundations on Lexington Drive south of Lake Cook Road

Tuesday, August 10, 2021

-
R.W. Dunteman Company placed asphalt pavement on Lexington Drive south of Lake Cook Road and framed and graded for the turn lane pavement on eastbound Lake Cook Road by Lexington Drive and sidewalk on Weiland Road north and south of Lake Cook Road
-
Areatha stripped forms on retaining Wall C and loaded out spoils from the cofferdam excavation at Buffalo Grove Road Bridge
-
Trine set frames on drainage structures and adjusted frames for water main valve vaults along eastbound Lake Cook Road between the Target and Walmart intersection and Hastings Lane
-
Home Towne installed foundations for traffic signal mast arms, light pole foundations, and handholes on southbound IL-83 by the Buffalo Grove Town Center intersection and installed conduit along southbound Weiland Road for the traffic signal interconnect
Wednesday, August 11, 2021

-
R.W. Dunteman Company poured pavement for the left turn lane and curb and gutter along eastbound Lake Cook Road from Lexington Drive to Hastings Lane, poured driveways, curb and gutter, and small segments of pavement at various locations along eastbound and westbound Lake Cook Road, and continued to excavate and prepare subgrade along westbound Lake Cook Road west of Weiland Road
-
Trine placed frames on drainage structures and adjusted existing frames along the curb line on eastboud Lake Cook Road east of Lexington Drive
-
Home Towne excavated for handholes on Weiland Road north of IL-83 and installed light pole foundations on Weiland Road between Buffalo Grove Road and IL-83
-
Trafic Services Inc switched traffic at the Lexington Drive intersection into a new configuration
-
TCP removed striping on northbound IL-83 by the Jewel intersection
Thursday, August 12, 2021

-
R.W. Dunteman Company placed asphalt pavement at the Walmart entrance, placed sidewalk on southbound Weiland Road, placed temporary pavement along the median of Lake Cook Road for the upcoming traffic switch, and continued to remove pavement, excavate and prepare subgrade along westbound Lake Cook Road from IL-83 to Weiland Road
-
Areatha continued working on the facing wall for retaining Wall C
-
Trine adjusted frames for drainage structures along eastbound Lake Cook Road east of Walmart
-
Home Towne install light pole foundations on Weiland Road and adjusted signal heads for traffic switch at Lexington Drive
-
Trafic Services Inc placed temporary pavement markings and switched traffic on Weiland Road
-
Industrial Fence Inc relocated temporary attenuators on Lake Cook Road for the Weiland Road traffic switch
Saturday, August 14, 2021

-
Areatha continued to frame retaining Wall C and excavated the cofferdam on the northwest corner of Buffalo Grove Road Bridge