CONSTRUCTION UPDATES

WEEK OF AUGUST 9, 2021

Monday, August 9, 2021        

  • R.W. Dunteman Company placed aggregate subbase on the eastbound Lake Cook Road Walmart truck entrance and removed existing pavement, and prepared subgrade at the northeast corner of Lake Cook Road and IL-83

  • Areatha stripped forms from retaining Wall C and continued to excavate the cofferdam for the Buffalo Grove Road Bridge widening

  • Home Towne drilled for light pole foundations on Lexington Drive south of Lake Cook Road

RWD_ NW Corner LCR  & IL83 08092021.jpg

Tuesday, August 10, 2021 

Areatha_WallCFraming_08102021.jpg
  • R.W. Dunteman Company placed asphalt pavement on Lexington Drive south of Lake Cook Road and framed and graded for the turn lane pavement on eastbound Lake Cook Road by Lexington Drive and sidewalk on Weiland Road north and south of Lake Cook Road

  • Areatha stripped forms on retaining Wall C and loaded out spoils from the cofferdam excavation at Buffalo Grove Road Bridge

  • Trine set frames on drainage structures and adjusted frames for water main valve vaults along eastbound Lake Cook Road between the Target and Walmart intersection and Hastings Lane

  • Home Towne installed foundations for traffic signal mast arms, light pole foundations, and handholes on southbound IL-83 by the Buffalo Grove Town Center intersection and installed conduit along southbound Weiland Road for the traffic signal interconnect

Wednesday, August 11, 2021

RWD_EBLCRC&GPour_08112021.jpg
  • R.W. Dunteman Company poured pavement for the left turn lane and curb and gutter along eastbound Lake Cook Road from Lexington Drive to Hastings Lane, poured driveways, curb and gutter, and small segments of pavement at various locations along eastbound and westbound Lake Cook Road, and continued to excavate and prepare subgrade along westbound Lake Cook Road west of Weiland Road

  • Trine placed frames on drainage structures and adjusted existing frames along the curb line on eastboud Lake Cook Road east of Lexington Drive

  • Home Towne excavated for handholes on Weiland Road north of IL-83 and installed light pole foundations on Weiland Road between Buffalo Grove Road and IL-83

  • Trafic Services Inc switched traffic at the Lexington Drive intersection into a new configuration

  • TCP removed striping on northbound IL-83 by the Jewel intersection

Thursday, August 12, 2021

Trine_CBAdjustmentsEBLCR_08122021.jpg
  • R.W. Dunteman Company placed asphalt pavement at the Walmart entrance, placed sidewalk on southbound Weiland Road, placed temporary pavement along the median of Lake Cook Road for the upcoming traffic switch, and continued to remove pavement, excavate and prepare subgrade along westbound  Lake Cook Road from IL-83 to Weiland Road

  • Areatha continued working on the facing wall for retaining Wall C

  • Trine adjusted frames for drainage structures along eastbound Lake Cook Road east of Walmart

  • Home Towne install light pole foundations on Weiland Road and adjusted signal heads for traffic switch at Lexington Drive

  • Trafic Services Inc placed temporary pavement markings and switched traffic on Weiland Road

  • Industrial Fence Inc relocated temporary attenuators on Lake Cook Road for the Weiland Road traffic switch

Friday, August 13, 2021

RWD_LexingtonDrTurnLaneFrame_08132021.jpg
  • R.W. Dunteman Company framed and poured left turn lanes on Lake Cook Road by Lexington Drive,   poured curb and gutter on eastbound Lake Cook Road between the Walmart and Target intersection to Hastings Lane, excavated and prepared subgrade along westbound Lake Cook Road between IL-83 and Weiland Road

  • Areatha frame the facing wall for retaining Wall C

  • Trine installed underdrain pipe along westbound Lake Cook Road between Buffalo Grove Road and IL-83

  • Home Towne installed detector loops by Lake Cook Road and Lexington Drive, poured foundations for traffic signal mast arms, light pole foundations, and handholes along Buffalo Grove Road and Weiland Road

  • Maintenance Coating Co relocated the temporary barrier wall on Weiland Road for the traffic switch

  • TCP changed the configuration at the IL-83 and Jewel intersection and the Lake Cook Road and Walmart intersection

  • Industrial Fence Inc relocated temporary attenuators on Weiland Road for the traffic switch

Saturday, August 14, 2021

Areatha Cofferdam Excavations 081420021.jpg
  • Areatha continued to frame retaining Wall C and excavated the cofferdam on the northwest corner of Buffalo Grove Road Bridge