CONSTRUCTION UPDATES
WEEK OF AUGUST 16, 2021
Monday, August 16, 2021
-
R.W. Dunteman Company removed pavement and prepared subgrade on northbound Lexington Drive and Walmart intersection, poured sidewalk on Weiland Road between Lake Cook Road and IL-83, and poured the westbound left turn lane pavement at the Lake Cook Road and Walmart intersection
-
Trine filled an abandoned water main on southbound Buffalo Grove Road by St Mary's Parkway and conducted general site clean up
-
Areatha poured the next segment of retaining wall C facing wall
-
Home Towne to install unit duct for street lighting on northbound Weiland Road between Buffalo Grove Road and IL-83 and installed conduit for traffic interconnects on southbound Weiland Road between IL-83 and Buffalo Grove Road
-
Trafic Services Inc switched traffic to a new configuration on Weiland Road between IL-83 to Pauline Drive
-
Maintenance Coating Co relocated the temporary concrete barrier wall on southbound IL-83 to preparation for the IL-83 traffic switch

Tuesday, August 17, 2021

-
R.W. Dunteman Company poured the median and curb and gutter on Lake Cook Road between Lexington Drive and Hastings Lane and excavated and graded, and placed aggregate subgrade at the southeast corner of Lexington Drive and at the corner of the Walmart intersection
-
Areatha striped forms from retaining wall Wall C
-
Trine installed pipe underdrain along westbound Lake Cook Road between IL-83 and Weiland Road
-
Home Towne installed unit duct for street lighting on southbound IL-83, installed light pole foundations on Weiland Road, and prepared traffic signals for the turn on at the IL-83 and Weiland Road intersection
-
Trafic Services Inc onsite to finish placing final signage and temporary pavement markings for the Weiland Road Stage switch
Wednesday, August 18, 2021

-
R.W. Dunteman Company poured the median and curb and gutter on Lake Cook Road west of Lexington Drive and completed earthwork along eastbound Lake Cook Road in preparation for the installation of foundations
-
Areatha drove piles and installed lagging for the temporary soil retention system on Buffalo Grove Road Bridge and installed a seal between the approach slab and pavement by Weiland Road Bridge
-
Trine remove existing storm sewer pipe and structures and set new frames and grates on drainage structures along the median gutter on eastbound Lake Cook Road from Walmart to the east limit
-
Home Towne installed conduit for traffic signals at the Lake Cook Road and Walmart intersection and poured light pole foundations and handholes along southbound Weiland Road
-
Maintenance Coating Co switched traffic on IL-83 and relocated the temporary concrete barrier wall along southbound IL-83
-
Industrial Fence Inc relocated temporary impact attenuators on IL-83 north of Lake Cook Road for the IL-83 traffic change
Thursday, August 19, 2021

-
R.W. Dunteman Company framed and poured concrete pavement along eastbound Lake Cook Road by the Walmart intersection, poured sidewalk along southbound IL-83 at the Buffalo Grove Town Center entrance, continued to place capping aggregate along westbound Lake Cook Road from Raupp Boulevard to Weiland Road
-
Areatha continued to excavate for the northwest wingwall footing on Buffalo GroveRoad Bridge, placed lagging behind the temporary soil retention system on the northwest corner of the bridge, and graded, framed, and installed rebar for the barrier wall located by the Weiland Road Bridge
-
Trine removed and replaced storm sewer structure and pipes on southbound IL-83 by retaining wall C
-
Home Towne installed conduit traffic interconnect on the crossing on westbound Lake Cook Road by IL-83, installed conduit for street lighting for driveway crossings on westbound Lake Cook Road between IL-83 and Weiland Road, and installed conduit and unit duct on southbound Weiland Road north of Lake Cook Road
-
Antigo broke concrete pavement on northbound Weiland Road between IL-83 and Lake Cook Road and on southbound Buffalo Grove Road from Buffalo Grove Road bridge to the south limit
Friday, August 20, 2021

-
R.W. Dunteman Company poured concrete pavement at the southeast corner of Lexington Drive and Lake Cook Road and at the southwest corner of the Walmart and Lake Cook Road intersection, continued to place and fine grade aggregate subgrade in preparation for concrete pavement along westbound Lake Cook Road between Raupp Boulevard and IL-83, and removed existing pavement at the northeast corner of Lake Cook Road and IL-8.
-
Areatha set forms for abutment footing at the northwest corner of the Buffalo Grove Road bridge
-
Trine continued to remove and replace sewer pipe and install new structures along IL-83 by retaining wall C
-
Home Towne installed conduit on southbound Weiland Road for traffic interconnect and installed unit duct for street lighting and turned on the traffic signals at IL-83 and Weiland Road and at Weiland Road and Buffalo Grove Road
-
Trafic Services Inc placed temporary pavement markings and signage to open the Weiland Road extension between IL-83 and Buffalo Grove Road
Saturday, August 21, 2021

-
R.W. Dunteman Company installed capping aggregate and fine grade in preparation for concrete pavement along westbound Lake Cook Road between Buffalo Grove Road and Weiland Road
-
Areatha framed footing for northwest abutment on Buffalo Grove Road Bridge and installed rebar for the barrier wall at the northwest corner of Weiland Road Bridge
-
Home Towne installed conduits for traffic signals along eastbound Lake Cook Road by the Walmart entrance