Monday, August 30, 2021        

  • R.W. Dunteman Company prepared for the concrete pavement pour of lanes 1 and 2 along westbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard, excavated and prepared subgrade on Weiland Road north of IL-83, and removed existing pavement along westbound Lake Cook Road from Weiland Road to the Target and Walmart intersection

  • Trine removed existing storm sewer pipe and structures on northbound Weiland Road north of Lake Cook Road

  • Areatha formed for the northwest corner abutment widening on Buffalo Grove Road bridge, drilled foundations, placed rebar, and poured concrete for foundations

  • Home Towne excavated for traffic signal foundations at the northeast and northwest corner of the Lake Cook Road and Target and Walmart intersection

Aretha_NWAbutFrameBGdBridge_08302021_edited.jpg

Tuesday, August 31, 2021 

RWD PCC Pavement 08312021.jpg
  • R.W. Dunteman Company poured concrete pavement for lanes 1 and 2 along westbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard, excavated and prepared subgrade along the median on IL-83, and removed existing pavement along westbound Lake Cook Road from Weiland Road to the Target and Walmart intersection

  • Trine removed existing storm sewer pipe and structures on northbound Weiland Road north of Lake Cook Road

  • Areatha formed for the northwest corner abutment widening on Buffalo Grove Road bridge, drilled foundations, placed rebar, and poured concrete for foundations

  • Home Towne install conduit for traffic signal and street lighting along westbound Lake Cook Road by Target

  • AC Iron tied rebar at the northwest abutment widening on Buffalo Grove Road Bridge

Wednesday, September 1, 2021

StevePiper_TreeRemWBLCR-1_09012021.jpg
  • R.W. Dunteman Company framed and prepared for pavement at various locations along westbound Lake Cook Road, removed existing pavement along westbound Lake Cook Road from Weiland Road to the Target and Walmart intersection, and prepared subgrade along northbound Weiland Road

  • Trine set new frames along westbound Lake Cook Road west of Weiland Road and reconstructed manholes along Weiland Road

  • Areatha formed for the northwest corner abutment widening on Buffalo Grove Road bridge, drilled foundations, placed rebar, and poured concrete for foundations

  • Home Towne drilled and framed traffic signal foundations at the southwest corner of Weiland Road and Lake Cook Road

  • Steve Piper removed and pruned trees that conflict with the installation of foundations

Thursday, September 2, 2021

Aretha_NWAbutPourBGdBridge-2_09022021_edited.jpg
  • R.W. Dunteman Company framed and prepared for pavement pours along westbound Lake Cook Road, removed the existing pavement along westbound Lake Cook Road from Weiland Road to the Target and Walmart intersection, prepared subgrade along northbound Weiland Road for the left turn lane on westbound Lake Cook Road, removed pavement on westbound Lake Cook Road by the Target, excavated subgrade and proof rolled on northbound Weiland Road south of Lake Cook Road, and placed capping on the IL-83 median north of Lake Cook Road

  • Trine removed and replaced storm sewer pipe and structures on northbound IL-83 south of Weiland Road

  • Areatha finished forming and poured concrete for the northwest corner abutment widening on Buffalo Grove Road bridge and drilled foundations, placed rebar, and poured concrete for foundations

  • Home Towne continued to install traffic signal foundations, handholes, and street lighting at the southwest corner of Lake Cook Road and Weiland Road

Friday, September 3, 2021

Trine_SSRCPRemIL-83_09032021.jpg
  • R.W. Dunteman Company poured concrete pavement along westbound Lake Cook Rd by Raupp Boulevard, IL-83, and Buffalo Grove Road and prepared subgrade for placement of aggregate subgrade along northbound Weiland Road south of Lake Cook Road

  • Trine removed existing storm sewer pipe and structures along northbound Weiland Road north of IL-83

  • Home Towne continued to install traffic signal foundations and handholes at the Lake Cook Road and Weiland Road and the Lake Cook Road and the Target and Walmart intersections

  • Areatha set forms for the northwest abutment wing wall at Buffalo Grove Road Bridge

Saturday, September 4, 2021

Aretha_NWAbutFrameBGdBridge_09042021_edited.jpg
  • Areatha set forms for the northwest abutment wing wall at Buffalo Grove Road Bridge