CONSTRUCTION UPDATES
WEEK OF AUGUST 30, 2021
Monday, August 30, 2021
-
R.W. Dunteman Company prepared for the concrete pavement pour of lanes 1 and 2 along westbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard, excavated and prepared subgrade on Weiland Road north of IL-83, and removed existing pavement along westbound Lake Cook Road from Weiland Road to the Target and Walmart intersection
-
Trine removed existing storm sewer pipe and structures on northbound Weiland Road north of Lake Cook Road
-
Areatha formed for the northwest corner abutment widening on Buffalo Grove Road bridge, drilled foundations, placed rebar, and poured concrete for foundations
-
Home Towne excavated for traffic signal foundations at the northeast and northwest corner of the Lake Cook Road and Target and Walmart intersection

Tuesday, August 31, 2021

-
R.W. Dunteman Company poured concrete pavement for lanes 1 and 2 along westbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard, excavated and prepared subgrade along the median on IL-83, and removed existing pavement along westbound Lake Cook Road from Weiland Road to the Target and Walmart intersection
-
Trine removed existing storm sewer pipe and structures on northbound Weiland Road north of Lake Cook Road
-
Areatha formed for the northwest corner abutment widening on Buffalo Grove Road bridge, drilled foundations, placed rebar, and poured concrete for foundations
-
Home Towne install conduit for traffic signal and street lighting along westbound Lake Cook Road by Target
-
AC Iron tied rebar at the northwest abutment widening on Buffalo Grove Road Bridge
Wednesday, September 1, 2021

-
R.W. Dunteman Company framed and prepared for pavement at various locations along westbound Lake Cook Road, removed existing pavement along westbound Lake Cook Road from Weiland Road to the Target and Walmart intersection, and prepared subgrade along northbound Weiland Road
-
Trine set new frames along westbound Lake Cook Road west of Weiland Road and reconstructed manholes along Weiland Road
-
Areatha formed for the northwest corner abutment widening on Buffalo Grove Road bridge, drilled foundations, placed rebar, and poured concrete for foundations
-
Home Towne drilled and framed traffic signal foundations at the southwest corner of Weiland Road and Lake Cook Road
-
Steve Piper removed and pruned trees that conflict with the installation of foundations
Thursday, September 2, 2021

-
R.W. Dunteman Company framed and prepared for pavement pours along westbound Lake Cook Road, removed the existing pavement along westbound Lake Cook Road from Weiland Road to the Target and Walmart intersection, prepared subgrade along northbound Weiland Road for the left turn lane on westbound Lake Cook Road, removed pavement on westbound Lake Cook Road by the Target, excavated subgrade and proof rolled on northbound Weiland Road south of Lake Cook Road, and placed capping on the IL-83 median north of Lake Cook Road
-
Trine removed and replaced storm sewer pipe and structures on northbound IL-83 south of Weiland Road
-
Areatha finished forming and poured concrete for the northwest corner abutment widening on Buffalo Grove Road bridge and drilled foundations, placed rebar, and poured concrete for foundations
-
Home Towne continued to install traffic signal foundations, handholes, and street lighting at the southwest corner of Lake Cook Road and Weiland Road
Friday, September 3, 2021

-
R.W. Dunteman Company poured concrete pavement along westbound Lake Cook Rd by Raupp Boulevard, IL-83, and Buffalo Grove Road and prepared subgrade for placement of aggregate subgrade along northbound Weiland Road south of Lake Cook Road
-
Trine removed existing storm sewer pipe and structures along northbound Weiland Road north of IL-83
-
Home Towne continued to install traffic signal foundations and handholes at the Lake Cook Road and Weiland Road and the Lake Cook Road and the Target and Walmart intersections
-
Areatha set forms for the northwest abutment wing wall at Buffalo Grove Road Bridge
Saturday, September 4, 2021

-
Areatha set forms for the northwest abutment wing wall at Buffalo Grove Road Bridge