CONSTRUCTION UPDATES
WEEK OF SEPTEMBER 06, 2021
Tuesday, September 7, 2021
-
R.W. Dunteman Company slip formed pavement on westbound Lake Cook Road between Raupp Boulevard and IL-83, removed existing pavement, prepared subgrade along westbound Lake Cook Road between Weiland Road and the Target and Walmart, and finished placing aggregate subgrade along northbound Weiland Road south of Lake Cook Road
-
Areatha formed and poured the northwest wing wall on Buffalo Grove Road Bridge and continued to drill foundations
-
Home Towne installed conduits for street lighting and traffic signals on Weiland Road south of Lake Cook Road
-
Maintenance Coating Co removed temporary concrete barriers on IL-83 north of Lake Cook Road

Wednesday, September 8, 2021

-
R.W. Dunteman Company slip formed pavement on westbound Lake Cook Road between Weiland Road and IL-83, excavated, prepared subgrade and placed aggregate subgrade for the IL-83 widening south of Weiland Road, and removed pavement and prepare subgrade along westbound Lake Cook Road between Weiland Road and the Target and Walmart intersection
-
Areatha stripped forms from the northwest wing wall on Buffalo Grove Road Bridge and cleaned off and prepared anchor bolts for the foundation columns
-
Home Town installed conduits for street lighting and traffic signals on northbound Weiland Road south of Lake Cook Road
-
Industrial Fence Inc removed temporary attenuators on northbound and southbound IL-83 north of Lake Cook Road
Thursday, September 9, 2021

-
R.W. Dunteman Company poured pavement along westbound Lake Cook Road by the Shell and poured curb and gutter gaps along eastbound Lake Cook Road east of Lexington Drive, removed temporary grindings and pavement along the Lake Cook Road median between IL 83 and Weiland Road, excavated subgrade and placed aggregate subgrade along westbound Lake Cook Road between Weiland Road and the Target
-
Areatha strip forms from the northwest wing wall on Buffalo Grove Road Bridge and started the demolition of the existing wing wall at the SW corner of the bridge
-
Home Towne excavated for traffic signal handholes along Lake Cook Road
Friday, September 10, 2021

-
R.W. Dunteman Company poured pavement on westbound Lake Cook Road right turn lane and double left turn lane at the IL-83 intersection and removed temporary pavement and placed aggregate subgrade along westbound Lake Cook Road between Weiland Road and the Target and Walmart intersection
-
Areatha removed the cofferdam from the northwest corner of the Buffalo Grove Road Bridge to prepare for the installation of the cofferdam at the southwest corner of the bridge and started to remove the existing wing wall at Buffalo Grove Road bridge
-
Home Towne poured traffic signal foundations and handholes on Lake Cook Road at the Target and Walmart intersection and the Weiland Road intersection
-
Trine reconstructed the existing sanitary manholes and valve vaults along northbound Weiland Road
Saturday, September 11, 2021

-
R.W. Dunteman Company broke and removed existing pavement on northbound Weiland Road north of Lake Cook Road and placed aggregate subgrade along westbound Lake Cook Road between Weiland Road and Target
-
Areatha placed sheet piles at the southwest corner of Buffalo Grove Road Bridge for the cofferdam installation