CONSTRUCTION UPDATES

WEEK OF SEPTEMBER 13, 2021

Monday, September 13, 2021        

  • R.W. Dunteman Company poured concrete pavement along eastbound Lake Cook Road for the left turn lanes at the Weiland Road intersection, graded and hauled off spoils, removed existing pavement, prepared subgrade, and placed aggregate subgrade along northbound Weiland Road north of Lake Cook Road

  • Areatha installed the cofferdam at the southwest corner of Buffalo Grove Road Bridge and installed a geocomposite wall drain on the back of the northwest abutment and wing wall of Buffalo Grove Road Bridge

  • Trine installed pipe underdrain on northbound Weiland Road north of IL-83 to Armstrong Drive

  • Home Towne framed hand holes on eastbound Lake Cook Road by Weiland Road and installed conduit for street lighting and traffic signals along westbound Lake Cook Road at the Weiland Road intersection

Trine_UnderdrainInstallationNBWeilandRd_09132021.jpg

Tuesday, September 14, 2021 

Areatha_BGRdBridgeSWWingwallDemo_09142021_edited.jpg
  • R.W. Dunteman Company graded and hauled off spoils and backfilled the northwest abutment and wing wall at Buffalo Grove Road Bridge, removed existing pavement, prepared subgrade along northbound Weiland Road north of Lake Cook Road, fine graded aggregate subgrade along westbound Lake Cook Road between Weiland Road and the Target and Walmart intersections for concrete pavement

  • Areatha demolished the existing abutment at the southwest corner of the Buffalo Grove Road Bridge and hydro excavated the remaining foundations 

  • Trine set frames and grates on existing drainage structures along westbound Lake Cook Road between Weiland Road to Raupp Boulevard

  • Home Towne drilled for traffic signal mast arms and excavated for traffic signal handholes at the Lake Cook Road and Target and Walmart intersection

Wednesday, September 15, 2021

RWD_WBLCRIL83TurnLanePCCPour-1_09152021.jpg
  • R.W. Dunteman Company poured pavement on westbound Lake Cook Road for the IL-83 and Buffalo Grove Road turn lanes, backfilled the northwest abutment and wing wall on Buffalo Grove Road Bridge, removed pavement on northbound Weiland Road, and fine graded aggregate subgrade along westbound Lake Cook Road for the upcoming pavement pour

  • Areatha demolished the existing abutment at the southwest corner of the Buffalo Grove Road Bridge and framed the remaining sections of the facing wall on the retaining wall

  • Trine to place frame and grates on drainage structures along westbound Lake Cook Road between Weiland Road and Target

  • Home Towne installed conduits for street lighting and traffic signal across the Lake Cook Road and Weiland Road intersection and installed detection loops for traffic signals at the Lake Cook Road and IL-83 intersection

  • Quality Saw cut concrete pavement on westbound Lake Cook Road by IL-83

Thursday, September 16, 2021

RWD_WBLCRPCCC&GPour_09162021.jpg
  • R.W. Dunteman Company slip formed curb and gutter along westbound Lake Cook Road between Raupp Boulevard and Weiland Road, removed pavement and prepared subgrade along northbound Weiland Road, framed and poured sidewalk along southbound Weiland Road, and pour pavement sleeper slab on Weiland Road at the northeast corner of Lake Cook Road and Weiland Road

  • Areatha demolished the existing abutment at the southwest corner of the Buffalo Grove Road Bridge

  • Trine installed pipe underdrain along Weiland Road north of Lake Cook Road and removed existing storm sewer pipe and structures on northbound Weiland Road

  • Home Towne installed conduits for street lighting on northbound Weiland Road and drilled light pole foundations on eastbound Lake Cook Road east of Lexington Drive

  • AC Iron tied rebar on the retaining by the sewer structures on IL -83

Friday, September 17, 2021

ACIron_WallCRebarInstallation_09172021.jpg
  • R.W. Dunteman Company slip formed westbound Lake Cook Road lanes 1 and 3 pavement between Weiland Road and the Target and Walmart intersection, prepared subgrade and placed aggregate subgrade along northbound Weiland Road north of Lake Cook Road, and slip formed curb and gutter along the westbound Lake Cook Road median between Raupp Boulevard and Weiland Road

  • Areatha excavated cofferdam at the southwest corner of Buffalo Grove Road Bridge

  • Trine removed existing storm sewer pipe and structures along northbound Weiland Road north of Lake Cook Road and installed pipe underdrain along Weiland Road north of Lake Cook Road

  • Home Towne drilled and poured light pole foundations on eastbound Lake Cook Road east of the Target and Walmart intersection

  • Quality Saw cut concrete pavement on westbound Lake Cook Road between Weiland Road and Target\

  • AC Iron tied rebar on the retaining wall by the sewer structures on IL-83

Saturday, September 18, 2021

IMG956609.jpg
  • R.W. Dunteman Company fine graded aggregate subgrade on northbound Weiland Road between IL-83 and Lake Cook Road in preparation for the concrete pavement pour and placed geotech fabric and aggregate subgrade along northbound Weiland Road north of Lake Cook Road

  • Areatha demolished the existing abutment at the southwest corner of the Buffalo Grove Road Bridge

  • Home Towne installed conduit for street lighting and traffic signals along eastbound Lake Cook Road east of Weiland Road