CONSTRUCTION UPDATES
WEEK OF SEPTEMBER 20, 2021
Monday, September 20, 2021
-
R.W. Dunteman Company slip formed concrete pavement for northbound Weiland south of Lake Cook Road, poured concrete median and curb and gutter along westbound Lake Cook Road by Weiland Road, excavated and prepared subgrade, prepared for aggregate backfill along northbound Weiland Road north of Lake Cook Road, removed various driveways along westbound Lake Cook Road, and graded for the new driveway construction
-
Areatha removed the existing wing wall and excavated for the new footing at the southwest corner of the Buffalo Grove Road bridge
-
Trine set frames for drainage structures on the Lake Cook Road median between Weiland Road and Raupp Boulevard
-
Home Towne drilled and installed rebar cages for light pole foundations along eastbound Lake Cook Road east of the Target and Walmart intersection
-
Quality onsite to saw cut pavement on westbound Lake Cook Road between Weiland Road and Target

Tuesday, September 21, 2021

-
R.W. Dunteman Company poured concrete pavement for various segments of lanes 1, 2 and 3 on westbound Lake Cook Road between Weiland Road and Target, poured curb and gutter on IL-83 and westbound Lake Cook Road, excavated and prepared subgrade, prepared for aggregate backfill along northbound Weiland Road north of Lake Cook Road, removed various driveways along westbound Lake Cook Road, and graded for the new driveway construction
-
Areatha framed the abutment and wing wall footing at the southwest corner of Buffalo Grove Road Bridge
-
Trine adjusted and set frames for drainage structures along the Lake Cook Road median between IL-83 and Raupp Boulevard and installed pipe underdrain on northbound Weiland Road north of Lake Cook Road
-
Home Towne excavated and framed handholes for traffic signals along eastbound Lake Cook Road between Walmart and Lexington Drive
-
Quality saw cut pavement on westbound Lake Cook Road between Weiland Road and Target
Wednesday, September 22, 2021

-
R.W. Dunteman Company poured concrete pavement on westbound Lake Cook Road for Weiland Road left turn lanes, poured pavement for lanes 1 and 2 on northbound Weiland Road south of Lake Cook Road, poured concrete median and curb and gutter at various locations along IL-83, excavated and prepared subgrade for the placement of the aggregate subgrade along northbound Weiland Road north of Lake Cook Road, removed various driveways along westbound Lake Cook Road, and graded for the new driveway construction
-
Areatha framed the southwest abutment and wing wall footing on Buffalo Grove Road Bridge, installed rebar for the new beam seats on the north abutment, and broke the existing approach slabs on the Buffalo Grove Road Bridge
-
Trine set frames for drainage structures along the Lake Cook Road median and installed pipe underdrain along northbound Weiland Road north of Lake Cook Road
-
Home Towne drilled, installed rebar cages, poured concrete for light pole foundations along eastbound Lake Cook Road west of Lexington Drive
-
Quality Saw saw-cut pavement that was poured along Lake Cook Road and Weiland Road
Thursday, September 23, 2021

-
R.W. Dunteman Company placed pavement for the left turn lanes on IL-83 north and south of Lake Cook Road, placed concrete median along IL-83 north of Lake Cook Road, installed curb and gutter along westbound Lake Cook Road, and placed subgrade aggregate on northbound Weiland Road north of Lake Cook Road
-
Areatha framed the southwest abutment and wing wall footing and broke the existing approach slabs on Buffalo Grove Road Bridge
-
Trine installed storm sewer pipe and structures at the northwest corner of the Buffalo Grove Road Bridge
-
Home Towne repaired detector loops along IL-83 north of Lake Cook Road and installed conduit for traffic signals along eastbound Lake Cook Road by Weiland Road
-
AC Iron tied rebar for the southwest abutment and wing wall footing on Buffalo Grove Road Bridge
Friday, September 24, 2021

-
R.W. Dunteman Company poured concrete pavement for the left turn lanes at the Target and Walmart along eastbound and westbound Lake Cook Road, poured concrete median and curb and gutter at various locations, and graded the aggregate subgrade on northbound Weiland Road north of Lake Cook Road in preparation for concrete pavement
-
Areatha poured the abutment and wing wall footing at the southwest corner of the Buffalo Grove Road Bridge and removed the existing approach slab from Buffalo Grove Road Bridge
-
Trine set frames for drainage structures on IL-83 and Weiland Road
-
Home Towne installed traffic loops under the new pavement and conduit for traffic signals along eastbound and westbound Lake Cook Road
Saturday, September 25, 2021

-
R.W. Dunteman Company fine graded aggregate subgrade on northbound Weiland Road between IL-83 and Lake Cook Road in preparation for the concrete pavement pour and placed geotech fabric and aggregate subgrade along northbound Weiland Road north of Lake Cook Road
-
Areatha demolished the existing abutment at the southwest corner of the Buffalo Grove Road Bridge
-
Home Towne installed conduit for street lighting and traffic signals along eastbound Lake Cook Road east of Weiland Road