CONSTRUCTION UPDATES
WEEK OF SEPTEMBER 27, 2021
Monday, September 27, 2021
-
R.W. Dunteman Company poured pavement for northbound Weiland Road by the Lake Cook Road intersection, poured concrete median, curb and gutter, and sidewalk at various locations, and removed existing pavement along southbound Buffalo Grove Road south of Lake Cook Road
-
Areatha removed the existing south abutment beam seats and framed the wing wall on the southwest corner of Buffalo Grove Road Bridge, and framed the new beam seats at the north abutment of Buffalo Grove Road Bridge
-
Home Towne drilled street lighting foundations along eastbound Lake Cook Road east of Lexington Drive, excavated and framed traffic signal handholes, and installed conduits at the southwest corner of Lake Cook Road and Lexington Drive
-
AC Iron tied rebar for southwest abutment and wing wall of Buffalo Grove Road Bridge
-
TCP onsite to adjust northbound IL-83 traffic closer to the median of the roadway

Tuesday, September 28, 2021

-
R.W. Dunteman Company poured pavement along westbound Lake Cook Road by the IL-83 and Buffalo Grove Road intersections, poured concrete median, curb and gutter, and sidewalk at various locations, and removed existing pavement along southbound Buffalo Grove Road south of Lake Cook Road
-
Areatha removed the existing south abutment beams, framed the wing wall at the southwest corner of Buffalo Grove Road Bridge, and framed the new beam seats at the north abutment of Buffalo Grove Road Bridge
-
Home Towne excavated and framed traffic signal handholes and installed conduit at the southwest corner of Lake Cook Road and Lexington Drive
-
Industrial Fence Inc removed temporary impact attenuators at Weiland Road and IL-83
-
Maintenance Coating Co removed the temporary concrete barrier wall from Weiland Road and IL-83
Wednesday, September 29, 2021

-
R.W. Dunteman Company poured concrete pavement on northbound and southbound Weiland Road north of Lake Cook Road, poured concrete median, curb and gutter, and sidewalk at various locations, removed existing pavement along southbound Buffalo Grove Road south of Lake Cook Road
-
Areatha framed and poured the southwest abutment widening and poured the new beam seats on the existing north abutment of Buffalo Grove Road Bridge, and removed the existing beam seats from the south abutment of Buffalo Grove Road Bridge
-
Home Towne drilled traffic signal foundations at the southwest corner of Lexington Drive and Lake Cook Road
Thursday, September 30, 2021

-
R.W. Dunteman Company poured pavement for left turn lane along eastbound Lake Cook Road by IL-83 and poured concrete median at various locations along Lake Cook Road, removed existing pavement along southbound Buffalo Grove Road, prepared subgrade, placed hot mix asphalt binder for driveways along westbound Lake Cook Road between Weiland Road and Buffalo Grove Road, and placed asphalt base at driveway entrances along westbound Lake Cook Road
-
Areatha framed and poured the new beam seats along the existing south abutment of the Buffalo Grove Road Bridge
-
Home Towne drilled for traffic signal foundations at the Target and Walmart intersection along Lake Cook Road
Friday, October 1, 2021

-
R.W. Dunteman Company poured pavement for left turn lanes on eastbound Lake Cook Road and poured concrete median at various locations along Lake Cook Road, graded for a sidewalk along noise abatement wall B, placed asphalt surface at driveway entrances along westbound Lake Cook Road, removed existing pavement, prepare subgrade, and place aggregate subgrade along southbound Buffalo Grove Road south of Lake Cook Road
-
Areatha set forms for the front and back face of the wing wall at the southwest corner of Buffalo Grove Road Bridge and framed the remaining sections of the facing wall on retaining wall C
-
Trine adjusted and set frames on drainage structures along Lake Cook Road and IL-83 median
-
Home Towne adjusted signal heads for the traffic switch along Lake Cook Road intersections and installed traffic signal foundations and handholes at Lexington Drive and the Target and Walmart intersections
-
TCP shifted westbound Lake Cook Road traffic onto the new pavement from the Target and Walmart intersection to Raupp Boulevard
-
Atlantic prepared beams for the final painting on Buffalo Grove Road Bridge
Saturday, October 2, 2021

-
R.W. Dunteman Company broke temporary pavement along eastbound Lake Cook Road just east of the Buffalo Grove Road intersection
-
Areatha poured the abutment wing wall at the southwest corner of the Buffalo Grove Road Bridge framed the retaining Wall C facing wall
-
Home Towne installed conduit for street lighting along eastbound Lake Cook Road from Lexington Drive to Hastings Lane and drilled light pole foundations along northbound Weiland Road between Buffalo Grove and IL-83