R.W. Dunteman Company poured sidewalk along Weiland Road, concrete median along Lake Cook Road, poured pavement on northbound Weiland Road south of Lake Cook Road, graded for sidewalk along Weiland Road and westbound Lake Cook Road, and broke and removed the existing pavement along southbound Buffalo Grove Road south of Lake Cook Road
-
Areatha removed forms from the southwest wing wall and backfilled the abutment on Buffalo Grove Road bridge, and poured the next segment of retaining wall C facing wall
-
Home Towne installed light pole foundations along westbound Lake Cook Road between IL-83 and Buffalo Grove Road

Tuesday, October 5, 2021

-
R.W. Dunteman Company poured pavement along northbound and southbound Weiland Road north of Lake Cook Road, worked on grading the median along Lake Cook Road between Raupp Boulevard and Target, broke and removed the existing pavement along southbound Buffalo Grove Road south of Lake Cook Road
-
Areatha removed the cofferdam at the southwest corner of Buffalo Grove Road Bridge, completed the closure pour between the wing wall and abutment on Buffalo Grove Road Bridge, and framed the last segment of retaining wall C
-
Home Towne installed traffic signal hand holes and street lighting foundations along westbound lake Cook Road from IL -83 and Weiland Road
-
TCP installed temporary pavement markings along westbound Lake Cook Road
Wednesday, October 6, 2021

-
R.W. Dunteman Company poured pavement for northbound Weiland Road north and south of Lake Cook Road, backfilled the southwest abutment wing wall at Buffalo Grove Road Bridge, removed existing pavement, prepared subgrade, and placed aggregate subgrade along southbound Buffalo Grove Road south of Lake Cook Road
-
Areatha backfilled the southwest abutment on Buffalo Grove Road Bridge and poured the final segment of retaining wall C
-
Home Towne installed conduit and unit duct for street lighting along eastbound Lake Cook Road east of Lexington Drive and installed light pole foundations along westbound Lake Cook Road by IL-83
-
Industrial Fence Inc removed the temporary impact attenuators on eastbound Lake Cook Road by Buffalo Grove Road Bridge
-
TCP removed the temporary concrete barrier along eastbound Lake Cook Road by Buffalo Grove Road Bridge and removed temporary pavement markings along eastbound Lake Cook Road
Thursday, October 7, 2021

-
Areatha assisted Clausen with the beam placement on Buffalo Grove Road Bridge
-
Clausen placed beams, installed diaphragms, and assembled bearings on Buffalo Grove Road Bridge
-
Trine set drainage frames on structures along Lake Cook Road median between Buffalo Grove Road and Target and on Weiland Road north of Lake Cook Road
Friday, October 8, 2021

-
R.W. Dunteman Company prepared for the left turn lane pavement along westbound Lake Cook Road at the Buffalo Grove Road intersection, removed existing pavement, prepared subgrade, and placed aggregate subgrade along southbound Buffalo Grove Road south of Lake Cook Road
-
Trine removed existing storm sewer pipes and structures on southbound Buffalo Grove Road south of Lake Cook Road
-
Areatha installed protective shielding and started installing decking material for the Buffalo Grove Road bridge deck
-
Home Towne installed conduit for traffic signals along westbound Lake Cook Road from Weiland Road to IL-83 and installed traffic signal foundations at the Weiland Road and Lake Cook Road intersection
-
Clausen installed diaphragms on Buffalo Grove Road Bridge Deck and drilled anchor bolts for the bearings
Saturday, October 9, 2021

-
R.W. Dunteman Company graded for curb and gutter on northbound Weiland Road, north and south of Lake Cook Road, broke existing median on Lake Cook Road by Raupp Boulevard, and broke pavement patches on northbound IL-83
-
Trine removed existing storm sewer pipe and structures on southbound Buffalo Grove Road south of Lake Cook Road, set drainage frames on structures along northbound Weiland Road, south of Lake Cook Road
-
Areatha framed fillets for Buffalo Grove Road Bridge deck
-
Home Towne installed unit duct for street lighting on westbound Lake Cook Road between Target and IL-83
-
Clausen drilled fixed bearing anchor bolts on Buffalo Grove Road Bridge