WEEK OF OCTOBER 5, 2020

Monday October 5, 2020

  • R.W. Dunteman Company poured concrete pavement lanes 2 and 3 on westbound Lake Cook Road from Lexington Drive to the Target truck entrance

  • Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between Weiland and the Target and Walmart entrance and on Weiland Road south of Lake Cook Road

  • Areatha framed the north abutment wing wall on Buffalo Grove Road Bridge

RWD_WBLCRLn2&3PCCPvt_10052020.jpg

Tuesday, October 6, 2020

  • R.W. Dunteman Company poured concrete pavement lanes 2 and 3 on westbound Lake Cook Road from the Target truck entrance to the Target and Walmart signalized entrance and placed aggregate subgrade, poured curb and gutter, and driveway for the Target truck entrance

  • Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrances and on Weiland Road south of Lake Cook Road

  • Areatha framed the north abutment wing wall on Buffalo Grove Road Bridge and removed forms for the retaining Wall A facing wall

  • Clausen replaced and tightened bolts for the steel diaphragms on Buffalo Grove Road Bridge

  • AC Iron tied rebar on the north abutment wing wall of Buffalo Grove Road Bridge

Trine_SSRCPInstallation_10062020.jpg

Wednesday, October 7, 2020

RWD_WBLCRGapPCCPvt_10072020.jpg
  • R.W. Dunteman Company removed existing pavement along eastbound Lake Cook Road between Buffalo Grove Road and IL-83 and poured pavement and curb and gutter gaps at various locations along northbound Buffalo Grove Road, northbound IL-83, and along westbound Lake Cook Road  

  • Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrance and on Weiland Road south of Lake Cook Road

  • Areatha framed the north abutment wing wall on Buffalo Grove Road bridge and completed structure excavation for retaining Wall F

  • AC Iron tied rebar on the north abutment wing wall of Buffalo Grove Road Bridge

Thursday, October 8, 2020

Areatha North Wingwall 1008020.jpg
  • R.W. Dunteman Company prepared for the concrete pavement pour along lane 1 on westbound Lake Cook Road from Hastings Lane to the Target and Walmart entrance and prepared subgrade along Lake Cook Road between Buffalo Grove Road and Weiland Road

  • Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrance and adjusted catch basins along westbound Lake Cook Road in preparation for the curb and gutter pour

  • Areatha framed the north abutment wing wall on Buffalo Grove Road Bridge and laid out the centerline of piles along Wall E & F

Friday, October 9, 2020

HTE_ConduitInstallation_10092020.jpg
  • R.W. Dunteman Company prepared for the concrete pavement pour along lane 1 on westbound Lake Cook Road from Hastings Lane to the Target and Walmart entrance by fine grading and installing dowel baskets and tie bars. R.W. Dunteman Company continued earth excavation along Lake Cook Road between Buffalo Grove Road and IL-83

  • Trine installed pipe underdrain along eastbound Lake Cook Road between Lake Cook Road and Raupp Boulevard and installed storm sewer pipes on northbound Buffalo Grove Road through the south abutment wall of Buffalo Grove Road Bridge

  • Areatha framed the north abutment wing wall on Buffalo Grove Road Bridge

  • Home Towne installed conduit for street lighting and traffic signals on eastbound Lake Cook Road by Buffalo Grove Road

Saturday, October 10, 2020

RWD_FineGradeEBLCRWestLimit_10102020.jpg
  • R.W. Dunteman Company worked on earth excavation of Lake Cook Road between Buffalo Grove Road and IL-83 and placed capping stone for the aggregate subgrade along eastbound Lake Cook Road from Raupp Boulevard to Buffalo Grove Road