CONSTRUCTION UPDATES

WEEK OF OCTOBER 12, 2020

Monday October 12, 2020

  • R.W. Dunteman Company installed dowel baskets and tie bars at the Lake Cook Road and Lexington Drive intersection and by the Target entrance. R.W. Dunteman graded and prepared for curb and gutter along westbound Lake Cook Road between Hastings Lane and the Target and Walmart entrances while preparing the subgrade along eastbound Lake Cook Road between IL-83 and Weiland Road 

  • Trine set frame and grates for storm sewer structures along westbound Lake Cook Road from Hastings Lane to the Target and prepared for installation of 16" & 8" water main valves along northbound Buffalo Grove Road by Lou Malnati’s

  • Industrial Fence Inc removed temporary attenuators along eastbound Lake Cook Road from Raupp Boulevard to Buffalo Grove Road

  • Traffic Control & Protection removed a temporary concrete barrier wall that is no longer required along eastbound Lake Cook Road from Raupp Boulevard to Buffalo Grove Road

RWD_EBLCRPGE_10122020.jpg

Tuesday, October 13, 2020

  • R.W. Dunteman Company poured concrete pavement on westbound Lake Cook Road lane 1 between Hastings Lane and the Target and Walmart entrance and continued preparing the subgrade along Lake Cook Road from IL-83 to Weiland Road

  • Trine removed and installed the storm sewer pipes and structures along southbound Weiland Road south of Lake Cook Road and installed new valve vaults and water main valves on the 16” water main along northbound Buffalo Grove Road by Lou Malnati’s  

  • Areatha poured the north abutment wing wall at Buffalo Grove Road Bridge

RWD_WBLCRLn1PCCPvt_10132020.jpg

Wednesday, October 14, 2020

Trine_LouMalnatisForcemain-3_10142020.jp
  • R.W. Dunteman Company prepared subgrade along eastbound Lake Cook Road between IL-83 and Weiland Road and installed Class D pavement patch at the Lake Cook Road and Weiland Road intersection after the contractor completed the storm sewer crossing underneath the roadway

  • Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrance and on Weiland Road south of Lake Cook Road

  • Areatha stripped forms on the north abutment of Buffalo Grove Road Bridge

  • Home Towne onsite to directional bore conduit for traffic signals and street lighting underneath the existing pavement at the Weiland Road and IL-83 intersection

Thursday, October 15, 2020

RWD_EBLCRLn2&3PCCPvt_10152020.jpg
  • R.W. Dunteman Company poured concrete pavement along eastbound Lake Cook Road lanes 1 and 2 between Raupp Boulevard and Buffalo Grove Road,on westbound Lake Cook Road by Hastings Lane, and at the northwest corner of Lake Cook Road and Lexington Drive. R.W. Dunteman Company prepared subgrade along eastbound Lake Cook Road from IL-83 to Weiland Road and placed the aggregate subgrade and backfilled the south abutment of Buffalo Grove Road Bridge

  • Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrance and on Weiland Road south of Lake Cook Road 

  • Areatha poured the north abutment wing wall closure at Buffalo Grove Road Bridge and prepared for drilling piles on retaining Wall F 

  • Home Towne continue directional boring from the southeast to the northeast corner of IL-83 and Weiland Road for traffic signals and lighting conduits

Friday, October 16, 2020

Areatha Wall F Piles 10162020.jpeg
  • R.W. Dunteman Company poured curb and gutter along westbound Lake Cook Road between Hastings Lane and the Target entrance and continued to prepare subgrade and place aggregate subgrade along eastbound Lake Cook Road between IL-83 and Weiland Road

  • Trine removed and installed of storm sewer pipes and structures along Weiland Road south of Lake Cook Road and also completed the installation of the 3” sanitary force main at the southeast corner of Lake Cook Road and IL-83

  • Areatha framed the Buffalo Grove Road bridge deck and drilled and set piles for retaining Wall F 

  • Home Towne installed conduit at the IL-83 and Weiland Road intersection for new street lighting and traffic signals

Saturday, October 17, 2020

Areatha Wall E Piles 10172020.jpg
  • Areatha framed the Buffalo Grove Road Bridge deck and drove piles for Retaining Wall E