CONSTRUCTION UPDATES
WEEK OF OCTOBER 19, 2020
Monday October 19, 2020
-
R.W. Dunteman Company removed existing pavement along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrances
-
Trine removed and installed the storm sewer pipes and structures along southbound Weiland Road south of Lake Cook Road and adjusted proposed drainage structures along eastbound Lake Cook Road between IL-83 and Weiland Road
-
Home Towne installed conduit for street lighting and traffic signals along westbound Lake Cook Road by Hastings Lane
-
Areatha framed the Buffalo Grove Road Bridge deck and set soldier piles for retaining Wall F

Tuesday, October 20, 2020
-
R.W. Dunteman Company removed existing pavement along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrances and backfilled behind the north abutment of Buffalo Grove Road bridge
-
Trine removed and installed the storm sewer pipes and structures along southbound Weiland Road south of Lake Cook Road and installed pipe underdrain on eastbound Lake Cook Road between IL-83 and Weiland Road
-
Home Towne continued installing conduit for traffic signals along westbound Lake Cook Road by Hastings Lane and Lexington Drive
-
Areatha framed the Buffalo Grove Road Bridge deck and set soldier piles for retaining Wall F

Wednesday, October 21, 2020

-
R.W. Dunteman Company removed existing pavement and driveways along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrances and backfilled behind the curb and gutter along westbound Lake Cook Road between Hastings Lane and Lexington Drive
-
Trine removed and installed the storm sewer pipes and structures along southbound Weiland Road south of Lake Cook Road
-
Home Towne continued installing conduits for the traffic signals along westbound Lake Cook Road by Lexington Drive and the Target and Walmart entrances
-
Areatha framed the Buffalo Grove Road Bridge deck and drove the soldier piles for retaining Wall E
Thursday, October 22, 2020

-
Trine removed and installed the storm sewer pipes and structures along southbound Weiland Road south of Lake Cook Road
-
Areatha framed the Buffalo Grove Road Bridge deck, drove the soldier piles for retaining Wall E, and removed the cofferdam at the south abutment on Buffalo Grove Road Bridge
-
Clausen installed anchor rods and bolts to set beam jacks on the south abutment on Buffalo Grove Road Bridge
Friday, October 23, 2020

-
Trine removed and installed the storm sewer pipes and structures along southbound Weiland Road south of Lake Cook Road
Saturday, October 24, 2020

-
R.W. Dunteman Company placed grinding materials at the temporary back entrance of the Walmart on eastbound Lake Cook Road and removed the cofferdam on Buffalo Grove Road Bridge
-
Areatha removed the cofferdam at the north and south abutment of Buffalo Grove Bridge