WEEK OF OCTOBER 25, 2021

Monday, October 25, 2021        

  • Areatha continued to frame supports and bracing and completed a dry run on Buffalo Grove Road Bridge

20211025_PH_PB_WSP_1999-17850_Areatha_SBBGRdBridgeDeckDryRun-2.jpg

Tuesday, October 26, 2021 

20211026_PH_PB_WSP_1999-17850_Areatha_SBBGRdBridgeDeckPour-2.jpg
  • R.W. Dunteman Company poured pavement on southbound Buffalo Grove Road by St Marys Parkway, poured various sections curb and gutter and median along Buffalo Grove Road south of Lake Cook Road, placed asphalt pavement along northbound Weiland Road north of Lake Cook Road

  • Areatha poured the stage 5 portion of the bridge deck on Buffalo Grove Road Bridge

  • Home Towne drilled light pole foundations along northbound Weiland Road and installed conduits for traffic signals on Buffalo Grove Road and westbound Lake Cook Road

  • Trine reconstructed and adjusted sanitary manholes along westbound Lake Cook Road and along southbound Buffalo Grove Road

  • IFI installed guardrail posts along Weiland Road by the west abutment of Weiland Road Bridge

Wednesday, October 27, 2021

20211027_PH_SA_GSG_1999-17850_RWD_NBWeilandRdHMAPour.jpg
  • R.W. Dunteman Company poured sidewalk along westbound Lake Cook Road and pour concrete driveways along northbound Weiland Road north of Lake Cook Road, poured concrete curb and gutter and driveways along St Mary’s parkway, and placed asphalt pavement on northbound Weiland Road and placed asphalt surface on Lexington Drive

  • Areatha removed equipment from the Buffalo Grove Road Bridge deck, poured and prepared for the north and south approach slabs, and set the remaining noise wall panel on the south side of Lake Cook Road

  • Home Towne excavated and framed handholes along westbound Lake Cook Road and installed unit duct for street lighting on southbound IL-83 south of Weiland Road

Thursday, October 28, 2021

20211021_PH_MA_GSG_1999-17850_RWD_EBLCRPCCPvtPour - Copy.jpg
  • R.W. Dunteman Company removed and replace concrete pavement panels at the AT&T manhole on eastbound Lake Cook Road and performed general site clean up

  • Areatha prepared the subgrade and placed aggregate subgrade for the north connector pavement on Buffalo Grove Road Bridge, and finished removing the existing approach pavement south of the bridge

  • Home Towne poured the controller foundation, handholes, and light pole foundations along eastbound and westbound Lake Cook Road, installed unit duct for street lighting along westbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard, installed traffic signal cables at the completed intersections along Lake Cook Road, installed and adjusted signal heads at the Weiland Road for the traffic switch along northbound and southbound Weiland Road

  • TSI adjusted traffic into the stage 6 configuration on Weiland Road

  • IFI removed temporary concrete barrier walls and temporary impact attenuators on southbound Buffalo Grove Road

Friday, October 29, 2021

20211029_PH_PB_WSP_1999-17850_Areatha_BGRdBridgeSouthSleeperSlabPour-2.jpg
  • R.W. Dunteman Company removed existing pavement, prepared subgrade, and placed aggregate subgrade at the Lake Cook Road and Buffalo Grove Road intersection, and graded and placed forms for sidewalk placement along eastbound Lake Cook Road

  • Areatha placed aggregate subgrade for the north connector pavement and poured the south sleeper slab on Buffalo Grove Road Bridge

  • Home Towne adjusted traffic signal heads for the traffic switch on Weiland Road and Lake Cook Road

  • AC Iron tied rebar for south approach sleeper slab on Buffalo Grove Road Bridge

  • TCP removed pavement markings on eastbound and westbound Lake Cook Road

Saturday, October 30, 2021

20211030_PH_MA_GSG_1999-17850_RWD_LCRPTempHMAPvtRem.jpg
  • R.W. Dunteman Company prepared for asphalt surface placement on northbound IL-83 and Lexington Drive

  • Areatha placed bidwell on Buffalo Grove Road Bridge deck

  • Home Towne installed unit duct for street lighting along westbound Lake Cook Road and framed handholes for traffic signals at Lake Cook Road and Weiland Road intersection