

CONSTRUCTION UPDATES
WEEK OF OCTOBER 26, 2020
Monday October 26, 2020
-
R.W. Dunteman Company excavated and removed spoils along eastbound Lake Cook Road from Buffalo Grove Bridge and graded and backfilled behind the curb and gutter along westbound Lake Cook Road between Lexington Drive and Target
-
Trine removed and installed the storm sewer pipes and structures along southbound Weiland Road south of Lake Cook Road
-
Areatha removed the cofferdam from the north abutment of Buffalo Grove Road bridge, set piles, and installed lagging and underdrain for retaining wall F
-
Home Towne shifted the guy wires for the temporary light pole on the northbound corner of Lake Cook Road and Weiland Road

Tuesday, October 27, 2020
-
R.W. Dunteman Company graded and backfilled behind the curb and gutter along westbound Lake Cook Road between Lexington Drive and Target, placed rip rap for storm sewer outfall at the south abutment of Buffalo Grove Road bridge and repaired potholes along Lake Cook Road
-
Trine removed the storm sewer pipes and structures along southbound Weiland Road south of Lake Cook Road
-
Areatha set soldier piles for retaining wall F
-
Clausen laid out bearings and prepared for the beam erection on Buffalo Grove Road Bridge

Wednesday, October 28, 2020

-
R.W. Dunteman Company excavated and backfilled behind the curb and gutter along westbound Lake Cook Road between Lexington Drive and Target, prepared for asphalt pavement on Lexington Drive by Lake Cook Road and backfilled the north abutment of Buffalo Grove Road Bridge
-
Trine removed the storm sewer pipes and structures along southbound Weiland Road south of Lake Cook Road
-
Areatha set soldier piles for retaining wall F
-
Home Towne installed conduit for traffic signals at the Lake Cook Road and IL-83 intersection
-
Clausen installed beams and diaphragms for Buffalo Grove Road Bridge
Thursday, October 29, 2020

-
R.W. Dunteman Company placed asphalt pavement and temporary pavement on southbound Lexington Drive north of Lake Cook Road and graded and backfilled behind the curb and gutter along westbound Lake Cook Road between Lexington Drive and Target
-
Trine removed the storm sewer pipes and structures along eastbound Lake Cook Road east of Weiland Road
-
Areatha framed the Buffalo Grove Road Bridge deck, installed lagging on retaining wall F, and drove piles on retaining wall E
-
Home Towne installed conduit for traffic signals and street lighting on Lake Cook Road by IL-83 and along northbound IL-83 by Jewel and NCH Hospital
-
Clausen setup, drilled in anchors and set templates for the jacking operation on Buffalo Grove Road Bridge
Friday, October 30, 2020

-
R.W. Dunteman Company excavated and prepared subgrade along eastbound Lake Cook Road between Weiland Road and Walmart and prepared aggregate subgrade along eastbound Lake Cook Road between Raupp Boulevard and Buffalo Grove Road in preparation for the pavement pours
-
Trine hauled out spoils, delivered backfill material, and performed general site cleanup in preparation for the night work at the Lake Cook Road and Weiland Road intersection
-
Areatha framed the Buffalo Grove Road Bridge deck and installed protective shielding and installed lagging on retaining wall F and retaining Wall E
-
Clausen drilled new diaphragm holes into the existing beams and installed anchor bolts on Buffalo Grove Road Bridge
Saturday, October 31, 2020

-
R.W. Dunteman Company installed pavement forms, dowel baskets and tie bars along eastbound Lake Cook Road in preparation for the lane 3 pavement pour between Raupp Boulevard and Buffalo Grove Road, prepared the concrete pavement at the Target signalized entrance and excavated and prepared subgrade along eastbound Lake Cook Road from Weiland Road and Walmart
-
Areatha framed the Buffalo Grove Road Bridge deck and installed piles for retaining wall B and finished the lagging installation for retaining wall E