Monday, November 1, 2021    

  • R.W. Dunteman Company poured concrete pavement along southbound Buffalo Grove Road by Lake Cook Road, placed concrete for residential driveways along southbound Buffalo Grove Road south of Lake Cook Road, and continued to break and remove temporary pavement located in the median along Lake Cook Road

  • Trine adjusted frames for manholes in the asphalt pavement along northbound Weiland Road north of Lake Cook Road and northbound IL-83 north of Lake Cook Road

  • Areatha set forms for the north and south approach slabs on Buffalo Grove Road Bridge and removed the existing pavement south of the Buffalo Grove Road bridge in preparation for the south connector pavement

  • Home Towne installed traffic signal cables along Lake Cook Road intersections, installed conduit for street lighting along IL-83, and installed electrical service cabinet at the IL-83 and Town Center intersection

20211101_PH_MA_GSG_1999-17850_RWD_SBBGRdPCCPour3.jpg

Tuesday, November 2, 2021 

20211102_PH_RGN_CCC_1999-17850_HomeTowne_WeilandRdLightingControllerCabinetInstallation.jp
  • R.W. Dunteman Company poured pavement southbound Buffalo Grove Road and placed curb and gutter along St Marys Parkway by Buffalo Grove Road and removed the existing pavement on southbound Weiland Road south of Lake Cook Road

  • Trine adjusted frames for manholes in asphalt pavement along northbound Weiland Road north of Lake Cook Road and on northbound IL-83 north of Lake Cook Road

  • Areatha finished grading for the sidewalk on the approach slabs, continued to clean up the Buffalo Grove Road bridge deck, and placed grout on the column anchor bolts for noise wall B

  • Home Towne set the lighting controller by Lake Cook Road and Weiland Road, excavated for controller foundations and drilled light pole foundations along Lake Cook Road, and installed luminaries at the IL-83 and Weiland Road intersection

Wednesday, November 3, 2021

20211103_PH_LN_WSP_1999-17850_Trine_IL-83F&GAdjustment.jpg
  • R.W. Dunteman Company framed, graded and poured concrete sidewalk on Lake Cook Road by Weiland Road and graded for sidewalk on Weiland Road north of Lake Cook Road, and prepared for the placement of topsoil on Buffalo Grove Road

  • Trine adjusted frames for manholes in asphalt pavement along northbound Weiland Road north of Lake Cook Road and northbound IL-83 north of Lake Cook Road

  • Areatha laid out forms for the north approach slab and completed general cleanup of the Buffalo Grove Road Bridge deck, and placed grout on the column anchor bolts for noise wall B

  • AC Iron tied rebar at the north approach slab on Buffalo Grove Road Bridge

  • Precision Pavement Marking prepared the pavement and installed permanent pavement markings along eastbound and westbound Lake Cook Road

  • Ruizscape spread topsoil along Buffalo Creek and placed topsoil along southbound IL-83 north of Lake Cook Road

  • Home Towne installed conduit for electrical service controller at the Lake Cook Road and the Target and Walmart intersection and excavated for traffic signal foundation on southeast corner of Lake Cook Road and IL-83

Thursday, November 4, 2021

20211104_PH_MA_GSG_1999-17850_Precision_WBLCRPermStriping.jpg
  • R.W. Dunteman Company framed, graded, and poured concrete pavement for the turn lane on Lake Cook Road by Buffalo Grove Road and on Lake Cook Road by Weiland Road, graded and poured concrete on northbound Weiland Road by Bucky's, and assisted Areatha with pavement removal on southbound Buffalo Grove Road south of the Buffalo Grove Road Bridge

  • Trine installed pipe underdrain along noise wall B

  • Areatha framed the south connector pavement for the Buffalo Grove Road Bridge and placed grout and  anchor bolts on noise wall B

  • AC Iron tied rebar at south and north approach slabs for Buffalo Grove Road Bridge

  • Precision Pavement Marking prepared the pavement and installed permanent pavement markings along eastbound and westbound Lake Cook Road

  • Ruizscape spread topsoil along Weiland Road south of Lake Cook Road and placed topsoil along southbound IL-83 south of Lake Cook Road behind retaining wall C

  • Home Towne drilled and poured concrete foundations for traffic signals, street lighting, and handholes at the Lake Cook Road and IL-83 intersection and poured traffic signal handholes at the Lake Cook Road and Weiland Road intersection

Friday, November 5, 2021

20211105_PH_LN_WSP_1999-17850_Trine_SBBGRdSSRemoval.jpg
  • R.W. Dunteman Company graded and poured sidewalk along westbound Lake Cook Road, prepared subgrade and placed aggregate subgrade on southbound Buffalo Grove Road south of the bridge, placed forms, and prepared for pavement placement along northbound Weiland Road south of Lake Cook Road

  • Trine removed existing storm sewer structures and pipe along southbound Buffalo Grove Road

  • Areatha formed the back parapet on the northwest wing wall and west edge of the sidewalk on Buffalo Grove Road Bridge

  • Precision Pavement Marking prepared the pavement and installed permanent pavement markings along eastbound and westbound Lake Cook Road

  • Ruizscape spread topsoil and installed remaining rip rap along Buffalo Creek

  • Home Towne framed handholes, installed conduit under driveway entrances on St Mary Parkway, and installed light pole bases along eastbound Lake Cook Road

Saturday, November 6, 2021

20211106_PH_PB_WSP_1999-17850_Areatha _BGRdBridgeNAppSlabPour1.jpg
  • R.W. Dunteman Company excavated and graded sidewalk along northbound Weiland Road south of Lake Cook Road and completed general site cleanup

  • Areatha poured the north and south approach slabs on Buffalo Grove Road Bridge

  • Precision Pavement Marking placed crosswalk markings and stop bars at intersections along Lake Cook Road

  • Ruizscape spread topsoil along Buffalo Creek and prepared topsoil for sod along IL-83 south of Lake Cook Road

  • Home Towne directional bore and installed unit duct at the Lake Cook Road and IL-83 intersection