Monday, November 8, 2021    

  • R.W. Dunteman Company poured concrete pavement on northbound Weiland Road for the left turn lane south of Lake Cook Road, installed aggregate base for driveway entrances along Weiland Road south of Lake Cook Road, and excavated and prepared the northeast corners of IL-83 and Buffalo Grove Road intersections with Lake Cook Road

  • Areatha poured the connector pavement on the south side of the Buffalo Grove Road Bridge

  • Home Towne directional bored for the traffic interconnect at the Lake Cook Road and Buffalo Grove Road intersection and excavated for the traffic signal foundations at the St Mary’s and Buffalo Grove Road intersection

  • Ruizscape spread topsoil by Buffalo Creek and Weiland Road and spread and prepared topsoil along southbound IL-83

20211108_PH_PB_WSP_1999-17850_Areatha_SBBGRdBridgePCCConnectorPvtPour.jpg

Tuesday, November 9, 2021 

20211109_PH_RGN_CCC_1999-17850_HomeTowne_LPErectionSBWeilandRd.jpg
  • R.W. Dunteman Company graded and placed pavement on Lake Cook Road by Buffalo Grove Road and on Lake Cook Road by Weiland Road, graded for sidewalk on westbound Lake Cook Road from Buffalo Grove Road to Raupp Boulevard, placed asphalt pavement on St Mary’s parkway, and placed asphalt surface on IL-83 north of Lake Cook Road

  • Areatha cleaned and prepared the horizontal construction joint for the sidewalk on the bridge deck

  • Home Towne installed light pole bases along eastbound Lake Cook Road, drilled and poured light pole foundations along northbound Weiland Road north of Lake Cook Road, and completed various traffic signal foundations and handholes for the Lake Cook Road and Weiland Road and the Buffalo Grove Road and St Mary Parkway intersections

  • Ruizscape placed additional rip rap at Buffalo Creek by the storm sewer outfalls on retaining Wall C and spread and prepared topsoil for the placement of sod along eastbound Lake Cook Road

Wednesday, November 10, 2021

20211110_PH_MA_GSG_1999-17850_RWD_SBBGRdPCCPvtPour.jpg
  • R.W. Dunteman Company prepared and poured pavement on southbound Buffalo Grove Road south of the Buffalo Grove Road Bridge, placed asphalt surface on Weiland Road and St Mary’s Parkway, graded for sidewalk placement along northbound IL-83 south of Weiland Road

  • Areatha framed and prepared for the sidewalk pour approaches and bridge deck of Buffalo Grove Road Bridge

  • Home Towne excavated and poured traffic signal foundations at Lake Cook Road and IL-83, installed light pole bases on Weiland Road, and installed new light poles along westbound Lake Cook Road

  • Ruizscape spread topsoil and prepared for sod placement along westbound Lake Cook Road

  • Quality grooved the Buffalo Grove Road Bridge deck and approaches

Thursday, November 11, 2021

20211111_PH_MA_GSG_1999-17850_RWD_LexingtonDrPCCSWPour_edited.jpg
  • Areatha framed the sidewalk approaches and bridge deck of the Buffalo Grove Road Bridge

Friday, November 12, 2021

20211113_PH_MA_GSG_1999-17850_RWD_WBLCRPCCSWFrame.jpg
  • R.W. Dunteman Company framed and poured sidewalk along Lake Cook Road at the Weiland Road and Lexington Drive intersections, graded and prepared for sidewalk along IL-83 by Weiland Road, and graded, prepared, and poured the medians along Lake Cook Road and Weiland Road

  • Areatha poured the sidewalk on approaches and bridge deck for Buffalo Grove Road Bridge

  • Home Towne erected light poles along eastbound Lake Cook Road  to Hastings Lane, poured light pole foundations along Weiland Road north of Lake Cook Road, and poured handholes for the traffic signals at Weiland Road and Lake Cook Road

  • Ruizscape prepared topsoil for sod placement along eastbound and westbound Lake Cook Road from the Target and Walmart intersection to Lexington Drive

Saturday, November 13, 2021

20211112_PH_PB_WSP_1999-17850_Areatha_SBBGRdBridgePCCSWPour1_edited.jpg
  • R.W. Dunteman Company broke the existing and temporary pavement along southbound Buffalo Grove Road north of Lake Cook Road, framed for the new sidewalk along westbound Lake Cook Road between IL-83 and Raupp Boulevard

  • Home Towne set light poles along eastbound Lake Cook Road and installed street lighting conduit along westbound Lake Cook Road by the Walmart intersection

  • TSI switched traffic on Buffalo Grove Road to stage 6 and installed new signage along Buffalo Grove Road