Sunday, November 15, 2020

  • Areatha continued to set forms for the northeast wing wall on Buffalo Grove Road Bridge

20201115_180758881_iOS.JPG

Monday, November 16, 2020

  • R.W. Dunteman Company placed curb and gutter from Raupp Boulevard to IL-83 and prepared and placed temporary pavement at the Lake Cook Road and IL-83 and Buffalo Grove Road intersections

  • Trine remove existing storm sewer structures and pipes at the northeast corner of Buffalo Grove Road and Lake Cook Road and continued the installation of the 20” water main along the Weiland Road extension

  • Areatha finished setting forms for the northeast wing wall on Buffalo Grove Road Bridge and poured the wing wall

  • Home Towne installed a handhole by Lexington Drive and Lake Cook Road and installed mast arm anchor bolts and conduit in wall F

  • Quality Saw cleaned, sandblasted, and placed joint sealer in new pavement along westbound Lake Cook Road from Hastings Lane to the Target and Walmart entrances

  • AC Iron installed shear connectors on piles 1-35 on retaining wall F

RWD Temp Pavement 11162020.jpg

Tuesday, November 17, 2020

  • R.W. Dunteman Company continued the placement of curb and gutter, temporary pavement, and driveway medians at various locations along Lake Cook Road

  • Trine continued the installation of 20" water main along the new Weiland Road extension east of Buffalo Grove Road

  • Areatha removed forms on the northeast wing wall and prepared for the upcoming bridge deck pour along Buffalo Grove Road Bridge 

  • Home Towne installed traffic signal handholes by Lexington Drive and Lake Cook Road and installed traffic signal conduit at the northeast corner of Buffalo Grove Road bridge

  • Quality Saw continued sealing joints along the new pavement on eastbound and westbound Lake Cook Road

  • AC Iron installed shear connectors on piles 1-24 on retaining wall E

20201118_113440000_iOS.JPG

Wednesday, November 18, 2020

IMG_5481.jpg
  • R.W. Dunteman Company continued to reconstruct driveway entrances along Lake Cook Road, placed temporary pavement at the Lake Cook Road and IL-83 intersection, removed existing pavement, and prepared the subgrade for the proposed pavement along eastbound Lake Cook Road by the Buffalo Grove Road Bridge

  • Trine continued to install 20" water main on the new Weiland Road extension east of Buffalo Grove Road

  • Areatha continued to prepare for the bridge deck pour on Buffalo Grove Road Bridge and completed a dry run with the paver

  • Home Towne framed handhole and controller foundations at the Lake Cook Road and Lexington Drive intersection and installed conduit for traffic signals at the Lake Cook Road and Buffalo Grove Road intersection

  • Quality Saw continued sealing joints along the new pavement on eastbound Lake Cook Road to Buffalo Grove Road

  • AC Iron installed rebar for retaining wall F

Thursday, November 19, 2020

20201119_090714.jpg
  • R.W. Dunteman Company placed asphalt binder at various locations along westbound Lake Cook Road, northbound IL-83, and various driveways along eastbound Lake Cook Road. R.W. Company prepared subgrade and placed aggregate subgrade along eastbound Lake Cook Road east of Buffalo Grove Road

  • Trine continued to install 20" water main on the new Weiland Road extension west of IL-83

  • Areatha poured the Stage 1 deck for the Buffalo Grove Bridge

  • Home Towne installed handholes, controller foundations, and light pole foundations by Lexington Drive

  • AC Iron installed rebar for the facing wall on retaining wall F

  • TCP updated pavement markings and shifted traffic to the winter traffic configuration along westbound Lake Cook Road between Hastings Lane and the Target and Walmart entrances

Friday, November 20, 2020         

20201120_163721000_iOS.JPG
  • R.W. Dunteman Company repaired potholes along Lake Cook Road between Raupp Boulevard and the Target and Walmart entrances, installed asphalt at various driveways, intersection returns along northbound IL-83, and prepared and poured lane 1 and 2 along eastbound Lake Cook Road at the Buffalo Grove Road intersection

  • Areatha excavated and placed forms for the south approach slab on Buffalo Grove Road Bridge

  • Trine adjusted existing valve vaults along eastbound Lake Cook Road west of IL-83

  • Home Towne installed handhole, controller foundations, and light pole foundations along Lake Cook Road from Hastings Lane to the Target and Walmart entrances

Saturday, November 21, 2020   

IMG_5489.jpg
  • R.W. Dunteman Company graded and poured temporary and permanent pavement along eastbound  Lake Cook Road by Buffalo Grove Road, IL-83, and Weiland Road and placed temporary pavement along northbound Buffalo Grove Road by Lake Cook Road

  • AC Iron placed rebar for the south approach sleeper slab on Buffalo Grove Road Bridge

  • Areatha assisted AC Iron with rebar placement