  • Trine Construction continues to install watermain along westbound Lake Cook Road
     

  • Home Towne continues to install wood poles for temporary street lighting along eastbound and westbound Lake Cook Road
     

  • R.W. Dunteman Company started to strip topsoil by pond area

Tuesday, March 17, 2020

HTE_TempTrafficSignalAerialCable_0317202
  • Trine Construction continues to install watermain along westbound Lake Cook Road
     

  • Home Towne continues to install wood poles for temporary street lighting along northbound Route 83, install temporary traffic signal heads and aerial cables by Route 83 and Jewel
     

  • R.W. Dunteman Company continues to strip topsoil by pond area

Wednesday, March 18, 2020

Trine_SSStructures_03192020.jpg
  • Trine Construction to install storm sewer pipes and structures by Route 83 and Weiland Road
     

  • Home Towne continue to install temporary traffic signal heads and aerial cables by Route 83 and Lake Cook Road, and install aerial cables along eastbound Lake Cook Road.

Thursday, March 19, 2020

Trine_SSPipes03182020.jpg
  • Trine Construction to install storm sewer pipes and structures by Route 83 and Weiland Road

Friday, March 20, 2020

Trine_AptakicisWM_03202020.jpg
  • Trine Construction continues to install watermain on Aptakisic Road
     

  • Home Towne continues to install wood poles and aerial cables for temporary street lighting along northbound and southbound Route 83, and install temporary traffic signal heads and aerial cables by Buffalo Grove Road and Lake Cook Road