Monday, April 13, 2020

HTE_TrafficSignalControllerRem_04140202.
  • Home Towne continues to remove existing traffic signal controllers, reinforced concrete foundations and poles along Lake Cook Road intersections
     

  • R.W. Dunteman Company continues to excavate dirt by pond, and placed cold patch along eastbound and westbound Lake Cook Road
     

  • Trafic Services Inc. to remove existing pavement markings, place temporary markings and switch to Maintenance of Traffic Stage 2 on Buffalo Grove Road

Tuesday, April 14, 2020

RWD_TempWeilandRdAlignment_04152020.jpg
  • Home Towne continues to remove existing traffic signal poles, handholes and reinforced concrete foundations on Lake Cook Road and Route 83 intersection
     

  • R.W. Dunteman Company continues to excavate dirt by pond area and strip topsoil on east of Weiland Road for temporary Weiland Road alignment
     

  • Maintenance Coating Company Traffic to remove existing pavement markings and switch to Maintenance of Traffic Stage 2 on southbound Route 83
     

  • C3 to perform construction layout for Stage 2 storm sewer work on northbound Buffalo Grove Road

Wednesday, April 15, 2020

Quality_SawCutCG_04152020 (002).jpg
  • Home Towne to adjust temporary signal heads by Raupp Boulevard and Lake Cook Road
     

  • R.W. Dunteman Company continues to excavate dirt and haul out by pond area, also on Weiland Road for temporary Weiland Road realignment
     

  • Quality Saw to saw cut curb, gutter and pavement on northbound Weiland Road and northbound Buffalo Grove Road south limit

Thursday, April 16, 2020

HardRock_SawCutPvt_04162020.jpg
  • Home Towne continues to adjust temporary signal heads by Raupp Boulevard and Lake Cook Road, also walked through to check all temporary street lighting poles, luminaires and 3 control boxes
     

  • R.W. Dunteman Company continues to excavate and haul out dirt at pond area and on Weiland Road for temporary Weiland Road realignment
     

  • Maintenance Coating Company to place temporary pavement marking tape and print, also switched traffic to Maintenance of Traffic Stage 2 on IL-83
     

  • Hardrock Cutting to saw cut pavement on northbound Buffalo Grove Road for storm sewer work

Friday, April 17, 2020

MCC_TempPvtMarking_04162020.jpg
  • Home Towne to perform final inspection of temporary street lighting controllers
     

  • Trine to deliver storm sewer pipes, structures and mobilize equipment on site by northbound Buffalo Grove Road
     

  • Trafic Services Inc. to adjust temporary pavement markings by Lake Cook Road and Buffalo Grove Road
     

  • Hardrock Cutting continues to saw cut pavement on northbound Buffalo Grove Road for storm sewer work
     

  • Maintenance Coating Company adjusts temporary pavement markings by Lake Cook Road and Route 83