Monday, April 20, 2020

Trine_SSRCPInstallation_04202020 (002).j
  • R.W. Dunteman Company continues to excavate and haul out dirt at pond area and on Weiland Road for temporary Weiland Road access
     

  • Trine to remove existing 30 inch reinforced concrete pipe run, install 42 inch reinforced concrete pipe run on northbound Buffalo Grove Road by south of creek
     

  • Trafic Services Inc. to place temporary pavement marking tape on Lake Cook Road/Route 83 and Lake Cook Road/Buffalo Grove intersections

Tuesday, April 21, 2020

RWD_TempWeilandSubgrade_04242020 (002).j
  • R.W. Dunteman Company continues to excavate and haul out dirt at pond area and on Weiland Road for temporary Weiland Road access, remove sidewalk on northbound Weiland Road and place asphalt grindings at the pond area to stabilize crusher equipment
     

  • Home Towne to remove concrete hand holes and traffic signal foundations on Lake Cook Road and Route 83 intersections
     

  • Trine continues to install storm sewer structures and reinforced concrete pipe run on northbound Buffalo Grove Road by south of creek

Wednesday, April 22, 2020

RWD_CrusherSetup_04232020 (002).jpg
  • R.W. Dunteman Company continues to excavate and haul out dirt on Weiland Road for temporary Weiland Road access and set up crusher on pond area
     

  • Compact temporary Weiland Road subgrade embankment
     

  • Home Towne continue to remove existing concrete hand holes, traffic signal foundations and light poles along Lake Cook Road and Route 83
     

  • Trine continue to remove existing storm sewer reinforced concrete pipe run, install new storm sewer reinforced concrete pipe run and storm sewer structures on northbound Buffalo Grove Road by south of creek

Thursday, April 23, 2020

Trine_SSStructureInstallation_04222020 (
  • R.W. Dunteman Company continues to excavate and haul out dirt on Weiland Road for temporary Weiland Road access, plus set up crusher on pond area
     

  • Compact temporary Weiland Rd subgrade embankment
     

  • Home Towne continues to remove existing concrete hand holes, traffic signal foundations and light poles along Route 83 and Buffalo Grove Road
     

  • Trine continues to remove existing storm sewer reinforced concrete pipe run, install new storm sewer reinforced concrete pipe run and storm sewer structures on northbound Buffalo Grove Road by south of creek

Friday, April 24, 2020

HTE_HHRem_04212020 (002).jpg
  • R.W. Dunteman Company continues to excavate and haul out dirt at pond area, place and compact aggregate base course on temporary Weiland Road and set up crusher on pond area
     

  • Trine continues to remove existing storm sewer reinforced concrete pipe run and storm sewer structures, install new storm sewer reinforced concrete pipe run and storm sewer structures on northbound Buffalo Grove Road
     

  • Home Towne continues to remove existing light poles and concrete foundations along Lake Cook Road