CONSTRUCTION UPDATES
WEEK OF April 27, 2020
Monday, April 27, 2020

-
R.W. Dunteman Company continues to excavate, haul out dirt, set up crusher at pond area and grade temporary Weiland Road access
-
Trine continues to remove existing storm sewer reinforced concrete pipe run and storm sewer structures, install new storm sewer reinforced concrete pipe run and storm sewer structures on northbound Buffalo Grove Road
-
Home Towne continues to remove street lighting poles and concrete foundations along Route 83 and Weiland Road
-
Areatha to install protective shield jack hammer and remove the deck overlay asphalt at Buffalo Grove Road bridge
Tuesday, April 28, 2020

-
R.W. Dunteman Company continues to excavate, haul out dirt, set up crusher at pond area and grade temporary Weiland Road access
-
Home Towne continue to remove street lighting poles and cables along Route 83, Lake Cook Road, and Weiland Road
-
Trine continues to remove existing storm sewer reinforced concrete pipe run and storm sewer structures, install new storm sewer reinforced concrete pipe run on northbound Buffalo Grove Road
-
Areatha continues to install protective shielding and remove the asphalt deck overlay at Buffalo Grove Road bridge
-
Traffic Control Protection to install temporary concrete barrier wall on Buffalo Grove Road bridge for closure
-
Industrial Fence Inc to install impact attenuator at Buffalo Grove Road bridge
-
Ruizscape to install inlet filters on northbound and southbound Route 83 and northbound Buffalo Grove Road, place riprap on storm sewer structure on southeast side of Buffalo Grove Creek
Wednesday, April 29, 2020

-
Trine to deliver storm sewer structures on Buffalo Grove Road, no field work due to rain
Thursday, April 30, 2020

-
Home Towne continues to remove street lighting poles and concrete foundations along Route 83 and Lake Cook Road
-
Trine continue to remove existing storm sewer reinforced concrete pipe run, install new storm sewer reinforced concrete pipe run and storm sewer structures on northbound Buffalo Grove Road
-
Areatha to layout saw cut lines on Buffalo Grove Road, bridge deck and sidewalk
Friday, May 1, 2020

-
Home Towne continues to remove existing street lighting poles on northbound and southbound Buffalo Grove Road
-
R.W. Dunteman Company continues to excavate and haul out dirt at pond area
-
R.W. Dunteman Company removes curb and gutter and top soil behind curb and gutter on southbound Route 83 in preparation for temporary pavement, and pothole patching at Buffalo Grove road from Aptakisic Road to Walgreens
-
Trine continues to remove existing storm sewer reinforced concrete pipe run and structures, install new storm sewer reinforced concrete pipe run and structures on northbound Buffalo Grove Road
-
Areatha to remove existing handrail along sidewalk on Buffalo Grove Road bridge
-
Quality Saw saw cut sidewalk and deck on Buffalo Grove Road bridge
Saturday, May 2, 2020

-
R.W. Dunteman continues to excavate and haul out dirt at pond area