Monday, May 11, 2020

Areatha_BuffaloGroveBridgeDeckRem_051220
  • R.W. Dunteman Company continues to strip paving forms on temporary by-pass pavement by Route 83, excavating and hauling out dirt at pond area
     

  • Areatha continues to remove Buffalo Grove Road bridge deck
     

  • Trine continues to install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road
     

  • Ruizscape to remove and replace inlet filters on northbound Route 83 and southbound Weiland Road

Tuesday, May 12, 2020

RWD_TempSWPour_05122020.jpg
  • R.W Dunteman Company to pour temporary by-pass pavement and temporary curb and gutter for Maintenance of Traffic Stage 3 on Route 83 southbound north of Lake Cook Road
     

  • R.W. Dunteman Company poured a temporary driveway for Shell and temporary Weiland Road, excavated temporary sidewalk along temporary Weiland Road and poured the temporary sidewalk, the contractor continues to stockpile topsoil in the pond area
     

  • Areatha continues to remove Buffalo Grove Road bridge deck on interior beams and beams 10-13
     

  • Trine continues to remove existing and install new storm sewer pipe and structures on southbound Weiland Road and northbound Buffalo Grove Road
     

  • Quality to saw cut Buffalo Grove Road bride deck

Wednesday, May 13, 2020

Areatha_BuffaloGroveBridgeDeckRem_051320
  • R.W. Dunteman Company to break pavement on northbound Buffalo Grove Road south of Lake Cook Road, haul topsoil to stockpile in the pond area
     

  • Areatha continues to remove Buffalo Grove Road bridge deck on interior beams and beams 13-9
     

  • Trine continues to install new storm sewer pipe and structures on southbound Weiland Road and northbound Buffalo Grove Road

Thursday, May 14, 2020

Areatha_BuffaloGroveBridgeWingWallRem_05
  • Areatha continues to remove Stage 1 southeast approach slab, southeast wing wall, sidewalk, curb and gutter adjacent to southeast approach slab on Buffalo Grove Rd bridge

Friday, May 15, 2020

RWD_MedianMilling_05152020.jpg
  • R.W Dunteman Company milled concrete medians on Lake Cook Road between Raupp Boulevard and Lexington Drive in preparation for future traffic staging
     

  • Areatha continues to break and remove abutment of Buffalo Grove Road bridge at southeast corner
     

  • Trine continues to remove existing storm sewer run, install new storm sewer pipe and structures on southbound Weiland Road and northbound Buffalo Grove Road

Saturday, May 16, 2020

RWD_PvtBreaking_05132020 (002).jpg
  • Trine continues to remove the existing storm sewer system and installs new storm sewer pipe and structures on southbound Weiland Road and northbound Buffalo Grove Road