CONSTRUCTION UPDATES

WEEK OF May 18, 2020

Monday, May 18, 2020

RWD_TempPvtPourWeilandRd_05202020.jpg
  • R.W. Dunteman Company to remove forms from temporary pavement, curb, gutter and sidewalk on temporary Weiland Road, plus finish excavation of ditch on both sides of temporary Weiland Road
     

  • Areatha continues to break concrete on top of the existing beams on Buffalo Grove Road bridge and clean up concrete chunks
     

  • Trine continues to install new storm sewer pipe and structures on southbound Weiland road and northbound Buffalo Grove Road
     

  • C3 surveyor onsite to shoot elevations of existing beam seats and top of beams 9-14

Tuesday, May 19, 2020

Trine_SSSturcrureInstallation_05192020.j
  • R.W. Dunteman Company to form northbound temporary pavement on Weiland Road north and south of Lake Cook Road
     

  • Home Towne continues to remove street lighting foundations and hand holes on Lake Cook Road and Buffalo Grove Road intersection
     

  • Areatha continues to break concrete on top of beams on Buffalo Grove Road bridge
     

  • Trine continues to remove existing storm sewer pipe and structures, install new storm sewer system on northbound Route 83 and northbound Buffalo Grove Road

Wednesday, May 20, 2020

Areatha_BGBridgeStudRem05182020.jpg
  • R.W. Dunteman to remove concrete debris from Weiland Road, pour temporary pavement on Weiland Road north and south of Lake Cook Road
     

  • Home Towne continues to break and remove street light pole foundations and hand holes along Lake Cook Road and Route 83
     

  • Areatha continues to remove shear studs on existing beams at Buffalo Grove Road bridge and remove concrete debris
     

  • Trine continues to remove existing storm sewer and install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road
     

  • Ruizscape onsite to place temporary stabilization for ditches next to temporary Weiland Road

Thursday, May 21, 2020

TSI_TempWeilandTempsStripingTrafficSwitc
  • R.W. Dunteman Company continues to remove concrete debris from Buffalo Grove Road, contractor cleans the temporary Weiland Road pavement in preparation for the opening of the temporary by-pass to traffic
     

  • Trine continues to remove existing storm sewer and install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road
     

  • Home Towne continues to break and remove street lighting foundations and hand holes along eastbound Lake Cook Road
     

  • Areatha continues removal of existing shear studs on the beams at Buffalo Grove Road bridge

Friday, May 22, 2020

IFI_ImpactAttenuatorInstallation_0522202
  • Trine continue to remove existing storm sewer pipe and structures, install new sewer system on northbound Route 83 and northbound Buffalo Grove Road
     

  • Areatha continues to clean up concrete debris from bridge deck removal on Buffalo Grove Road bridge
     

  • Trafic Services Inc. switched traffic between Weiland Road and temporary Weiland Road south of Lake Cook Road
     

  • Industrial Fence Inc. to install temporary impact attenuators by ComEd pole on temporary Weiland Road