Tuesday, May 26, 2020

Trine_SSRCPLateralInstallation_05302020_
  • R.W. Dunteman Company to trip topsoil on eastbound Lake Cook Road, and haul concrete debris to crusher at the pond area
     

  • Areatha to drill holes on south abutment on Buffalo Grove Road bridge to prepare for bearing replacement
     

  • Trine continues to remove existing storm sewer and install new storm sewer system along northbound Route 83 and northbound Buffalo Grove Road
     

  • Home Towne continues to break and remove traffic signal pole foundations, handholes, and traffic controller foundations along Lake Cook Road

Wednesday, May 27, 2020

RWD_LCRTempPvtGrading_05262020.jpg
  • R.W. Dunteman Company continues to excavate and grade dirt for temporary pavement along eastbound Lake Cook Road between Mobile and Walmart, plus remove curb, gutter and sidewalk for the temporary pavement
     

  • Trine continues to remove existing storm sewer and install new storm sewer system along northbound Route 83 and northbound Buffalo Grove Road
     

  • Areatha to magnetic particle test existing bridge beams at Buffalo Grove Road bridge on top flange for defects after shear stud removal
     

  • Clausen to remove existing steel abutment diaphragms and prepare for beam jacking operation to remove the existing bridge bearings on south Abut at Buffalo Grove Road bridge

Thursday, May 28, 2020

Clausen_JackingBracketInstallation_05272
  • R.W. Dunteman Company continues to excavate and grade dirt for temporary pavement on eastbound Lake Cook Road between Mobile and McDonalds, plus remove curb, gutter and sidewalk on eastbound Lake Cook Road
     

  • Home Towne continues to break and remove traffic signal pole foundations, handholes, traffic controller foundations along Lake Cook Road
     

  • Trine continues to remove existing storm sewer and install new storm sewer system along northbound Route 83 and northbound Buffalo Grove Road
     

  • Areatha breaks the north approach slab in preparation for removal and clean up concrete debris on Buffalo Grove Road bridge
     

  • Clausen continues to drill anchor bolts and install jacking brackets on Buffalo Grove Road bridge to prepare for beam jacking operations

Friday, May 29, 2020

Areatha_MagneticParticleTestingBGRBridge
  • R.W. Dunteman Company continues to excavate and grade for temporary pavement on eastbound Lake Cook Road between Walmart and Weiland Road
     

  • R.W. Dunteman Company removes curb, gutter, sidewalk and topsoil on eastbound Lake Cook Road, and install forms for temporary pavement on Lake Cook Road
     

  • Trine continues to remove existing storm sewer and install new storm sewer system along northbound Route 83 and northbound Buffalo Grove road
     

  • Areatha continues to break north App. Slab and clean up debris on Buffalo Grove Road bridge, also mobilized soldier piles for temporary earth retention system
     

  • Clausen continues to drill anchor bolts and install jacking brackets on Buffalo Grove Road bridge to prepare for beam jacking operations

Saturday, May 30, 2020

RWD_LCRTempPvtFraming_05302020.jpg
  • R.W. Dunteman continues to grade and frame in preparation for temporary pavement along eastbound Lake Cook Road from Weiland Road to McDonalds
     

  • Trine continues to remove existing storm sewer and install new storm sewer system along northbound Route 83 and northbound Buffalo Grove Road