Monday, May 4, 2020

RWD_CGRem_05052020.jpg
  • R.W. Dunteman Company continues to excavate and haul out dirt at detention pond and remove top soil
     

  • R.W. Dunteman Company excavated dirt behind curb and gutter on southbound Route 83 north of Lake Cook Road, pouring temporary by-pass pavement for temporary Weiland Road
     

  • Areatha continues to remove east sidewalk on Buffalo Grove Road bridge
     

  • Trine continues to remove existing storm sewer pipe and structures, install new storm sewer pipe and structures on northbound Buffalo Grove Road

Tuesday, May 5, 2020

Trine_SSRCPInstallation_05042020.jpg
  • R.W. Dunteman Company continues to excavate and haul out dirt at detention pond
     

  • R.W. Dunteman Company continues to remove curb and gutter, driveway, side walk and median on northbound Weiland Road south of Lake Cook Road and saw cut temporary Weiland Road longitudinal joint
     

  • Home Towne continues to remove street lighting foundations, controller foundations and hand holes on Buffalo Grove Road and Lake Cook Road intersection
     

  • Areatha continues to remove east sidewalk on Buffalo Grove Road bridge
     

  • Trine continues to remove existing storm sewer pipe structures, install new storm sewer pipe and structures on northbound Buffalo Grove Road

Wednesday, May 6, 2020

Trine_SSStructureInstallation_05072020.j
  • R.W. Dunteman Company continues to excavate and haul out dirt at detention pond
     

  • R.W. Dunteman Company continues to remove concrete driveway, existing curb and gutter, excavate dirt for temporary pavement and install forms for proposed curb and gutter on southbound Route 83
     

  • Home Towne continues to remove traffic signal foundation on northeast corner of Buffalo Grove Road and Lake Cook Road
     

  • Areatha to demo and remove east parapet wall at Buffalo Grove Road bridge
     

  • Trine continues to remove existing storm sewer pipe structures, install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road

Thursday, May 7, 2020

RWD_TempCGFormWork_05062020 (002).jpg
  • R.W. Dunteman Company continues to excavate and haul out dirt at detention pond, plus excavate temporary pavement on southbound Buffalo Grove Road
     

  • Trine continues to remove existing storm sewer pipe structures, install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road

Friday, May 8, 2020

RWD_TempPvtPourWeiland Rd_05042020.jpg
  • R.W. Dunteman Company continues to excavate and haul out dirt at detention pond, pothole patching along Lake Cook Road and place temporary access for driveways by Jewel, Walgreens and Steepleview apartment complex
     

  • R.W. Dunteman Company continues to excavate for temporary pavement on northbound Weiland Road, pour temporary by-pass pavement and temporary curb and gutter on southbound route 83 for Maintenance of Traffic Stage
     

  • Home Towne continues to remove street lighting pole foundations along northbound Buffalo Grove Road
     

  • Areatha continues to demo and remove bridge deck and beams 13 and 14 at Buffalo Grove Road bridge
     

  • Trine continues to remove existing storm sewer pipe structures, install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road

Saturday, May 9, 2020

Trine_SSRCPRem_05062020.jpg
  • Trine to excavate and haul excess backfill material from storm sewer installations on northbound Buffalo Grove Road