CONSTRUCTION UPDATES

WEEK OF June 1, 2020

Monday, June 1, 2020

  • R.W. Dunteman Company placed temporary concrete by-pass pavement and temporary sidewalk on eastbound Lake Cook Road, also adjusted catch basin frames along eastbound Lake Cook Road for new temporary pavement
     

  • Home Towne poured concrete foundation for electrical service by southwest corner of Walmart and Lake Cook Road intersection
     

  • Trine continues to remove existing storm sewer and install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road

cement.png

Tuesday, June 2, 2020

  • R.W. Dunteman Company placed asphalt for temporary driveway at the Mobil gas station along Lake Cook Road, also repaired driveway entrance by Jewel Osco along IL-83
     

  • R.W. Dunteman Company placed a temporary concrete by-pass pavement on eastbound Lake Cook Road for Maintenance of Traffic Stage 2A
     

  • Home Towne installed equipment for the new electrical service line on southwest corner of Walmart and Lake Cook Road intersection
     

  • Trine continues to remove existing storm sewer and install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road

electric%20lighting_edited.png

Wednesday, June 3, 2020

large scoop machine.png
  • Trine continues to remove existing storm sewer and install new storm sewer pipe and structures on northbound Route 83, the Contractor also installed new manhole and sanitary sewer forcemain for Lou Malnati's along Buffalo Grove Road
     

  • Clausen continues to prepare for lifting the beams of Buffalo Grove Road bridge
     

  • R.W. Dunteman Company start operating crusher and collected aggregate samples for testing gradations, plus grade topsoil in pond area

Thursday, June 4, 2020

  • Trine continues to remove existing and install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road, also perform pressure test for Lou Malnati's 4" sanitary sewer
     

  • Clausen installed hydraulic units by north and south abutments of Buffalo Grove Road bridge to prepare for beam lift
     

  • R.W. Dunteman Company place hot mix asphalt patches for storm sewer laterals on southbound Buffalo Grove Road, also prepare the ground for the concrete plant on Aptakisic Road

overpass.png

Friday, June 5, 2020

  • Trine continues to remove existing and install new storm sewer pipe and structures on northbound Route 83, also the Contractor placed temporary frames and grates along southbound Buffalo Grove Road
     

  • IFI install temporary impact attenuators along eastbound Lake Cook Road for upcoming traffic switch into Maintenance of Traffic Stage 2A
     

  • Sanco set temporary concrete barrier wall and drill pins into the wall along eastbound Lake Cook Road
     

  • R.W. Dunteman Company removes existing driveway and place asphalt for temporary driveway and temporary pavement along northbound Weiland Road north and south of Lake Cook Road

road.png

Saturday, June 6, 2020

  • Trine continues to remove existing and install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road
     

  • R.W. Dunteman Company frames foundation for concrete batch plant at short Aptakisic Road
     

  • Antigo onsite to break existing pavement along Weiland Road and Buffalo Grove Road
     

  • Home Towne perform maintenance on temporary street lights on Buffalo Grove Road, Route 83, Weiland Road and Lake Cook Road