CONSTRUCTION UPDATES
WEEK OF JUNE 15, 2020
Monday, June 15, 2020

-
R.W. Dunteman Company prepares subgrade and place aggregate subgrade for Weiland Road and along northbound Buffalo Grove Road, south of Lake Cook Road
-
R.W. Dunteman Company works on removing curb and gutter along westbound Lake Cook Road for temporary pavement needed in Stage 2B
-
Trine continues to remove existing storm sewer and install new storm sewer pipe and structures along northbound IL-83 and along westbound Lake Cook Road
Tuesday, June 16, 2020

-
R.W. Dunteman Company continues to prepare along northbound Buffalo Grove Road at Aptakisic Intersection and continue building embankment along Weiland Road
-
R.W. Dunteman Company removes and stockpiles of topsoil along westbound Lake Cook Road in preparation for Stage 2B temporary pavement
-
Home Towne continues to break and remove traffic signal foundations by Weiland Road and Lake Cook Road intersection
-
Trine continues to remove existing storm sewer and install new storm sewer pipe and structures along northbound IL-83 and along westbound Lake Cook Road
Wednesday, June 17, 2020

-
R.W. Dunteman Company continues to prepare subgrade on Weiland Road and Buffalo Grove Road and place aggregate subgrade along Buffalo Grove Road
-
R.W. Dunteman Company removes topsoil and excavated to subgrade along westbound Lake Cook Road in preparation for temporary pavement, and also removed existing pavement on northbound Buffalo Grove Road, north of Lake Cook Road
-
Trine continues to remove existing storm sewer and install new storm sewer pipe and structures along northbound IL-83 and along westbound Lake Cook Road
-
Home Towne continues to remove existing light pole and traffic signal foundations by the Buffalo Grove Road and Lake Cook Road intersection
-
Areatha to install protective shield caps at north abutment and prepare for backwall removal
Thursday, June 18, 2020

-
R.W. Dunteman Company continues to remove pavement along northbound Buffalo Grove Road, place asphalt patches on Buffalo Grove Road, storm sewer crossings south of Lake Cook Road, and place aggregate subgrade
-
Home Towne excavated trench and place conduit for the new traffic signals at the Weiland Road/St Mary's & Buffalo Grove Road intersection
-
Trine continues to remove existing storm sewer and install new storm sewer pipe and structures along northbound IL-83 and along westbound Lake Cook Road
-
Areatha to drive soldier piles and install lagging for the temporary earth retention system at the south abutment on Buffalo Grove Road bridge
-
The Contractor continues the removal of the south abutment backwall at Buffalo Grove Road bridge
Friday, June 19, 2020

-
R.W. Dunteman Company patch potholes along the Lake Cook Road median
-
R.W. Dunteman Company continues the removal of topsoil along eastbound Lake Cook Road in preparation for temporary pavement, and also continues to place aggregate subbase along Buffalo Grove Road
-
Trine continues to remove existing storm sewer and install new storm sewer pipe and structures along northbound IL-83 and along westbound Lake Cook Road, the Contractor also installs 6" pipe underdrain on northbound Buffalo Grove Road
-
Areatha working on removing the existing backwall on the south abutment backwall of Buffalo Grove Road bridge
Saturday, June 20, 2020

-
Trine continues to remove existing storm sewer and install new storm sewer pipe and structures along northbound IL-83 and along westbound Lake Cook Road
-
Home Towne loadout existing light poles and deliver them to the Village of Buffalo Grove