CONSTRUCTION UPDATES
WEEK OF JUNE 29, 2020
Monday, June 29, 2020

-
R.W. Dunteman Company to install asphalt patches along IL-83 and prepare the subgrade for Weiland Road east of IL-83
-
Home Towne continues to break and remove concrete foundations from existing traffic signals and hand holes along Lake Cook Road
-
Trine continues to remove existing storm sewer and install new storm sewer pipe and structures along westbound Lake Cook Road.
-
Trine also resumes the installation of the 12” watermain on the north side of Lake Cook Road
-
Atlantic Painting on site to clean the contaminated material off the existing bearings and beams on the north and south abutment of the Buffalo Grove Rd Bridge. Contractor continues to clean and apply protective coating on existing beam webs
Tuesday, June 30, 2020

-
R.W. Dunteman Company continues to install asphalt patches along Lake Cook Road between Weiland Road and Target to repair the pavement from the proposed drainage laterals
-
R.W. Dunteman Company continues to prepare subgrade along Weiland Road East of IL-83
-
Home Towne continues to remove existing street light foundations along Lake Cook Road
-
Trine continues to remove existing storm sewer and install new storm sewer pipe and structures along westbound Lake Cook Road
-
Trine continues the installation of the 12” watermain on the north side of Lake Cook Road near IL-83
-
Atlantic Painting on site to clean the contaminated material off the existing bearings and beams on the north and south abutment of the Buffalo Grove Rd Bridge. Contractor continues to clean and apply protective coating on existing beam webs
Wednesday, July 1, 2020

-
R.W. Dunteman Company continues to install asphalt patches along Lake Cook Roads between Weiland Road and Target to repair the pavement from the proposed drainage laterals
-
R.W. Dunteman Company continues to prepare subgrade along Weiland Road East of IL-83 and places temporary pavement along westbound lake Cook Road for the upcoming traffic switch
-
Home Towne continues to remove existing street lighting, controller, and traffic signal foundations along Lake Cook Road
-
Trine completed the removal and installation of new storm sewer pipe and structures along westbound Lake Cook Road
-
Trine continues the installation of the 12” watermain on the north side of Lake Cook Road near IL-83
-
Atlantic Painting on site to clean the contaminated material off the existing bearings and beams on the north and south abutment of the Buffalo Grove Rd Bridge. Contractor continues to clean and apply protective coating on existing beam webs
Thursday, July 2, 2020

-
R.W. Dunteman Company to place a concrete patch along IL-83 to repair the pavement after completing storm sewer installations
-
R.W. Dunteman Company fine grades subgrade aggregate along Buffalo Grove Road in preparation for pouring the concrete pavement, they also continue to prepare for the placement of temporary pavement along eastbound Lake Cook Road near Lexington Drive
-
Trine mobilized equipment and material to the north leg of Buffalo Grove Road to start working on installing the storm sewer next week, Contractor continues the installation of the 12” watermain on the north side of Lake Cook Road near IL-83
-
Atlantic Painting on site to clean the contaminated material off the existing bearings and beams on the north and south abutment of the Buffalo Grove Rd Bridge. Contractor continues to clean and apply protective coating on existing beam webs