Monday, June 8, 2020

RWD_PCCPvtRemBGRd_06102020.jpg
  • R.W. Dunteman Company framed and poured temporary sidewalk ramp at Walmart and Lake Cook Road
     

  • Contractor placed temporary by-pass pavement and driveway along Weiland Road, and also started the removal of existing pavement along the south leg of Buffalo Grove Road
     

  • Home Towne adjusted signal heads for Maintenance of Traffic switch into Stage 2A along Lake Cook Road
     

  • Trine continues to remove existing and install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road
     

  • Traffic Control & Protection installed temporary striping and signage for Stage 2A traffic switch along Lake Cook Road

Tuesday, June 9, 2020

Trine_RCPInstallationBGRd_06092020 (002)
  • R.W. Dunteman Company continues to place temporary by-pass pavement, driveway, and sidewalk along Weiland Road and Lake Cook Road
     

  • Contractor continues the removal of existing pavement along the south leg of Buffalo Grove Road
     

  • Home Towne adjusted temporary traffic signal cameras along Lake Cook Road intersections due to the recent traffic switch
     

  • Trine continues to remove existing storm sewer and install new storm sewer pipe and structures on northbound Route 83 and northbound Buffalo Grove Road
     

  • Areatha onsite to continue removal of the bridge deck along Buffalo Grove Road bridge
     

  • Sanco onsite to install and pin temporary concrete barrier wall along Lake Cook Road
     

  • IFI install temporary attenuators for the temporary barrier wall being placed along Lake Cook Road

Wednesday, June 10, 2020

HomeTowne_PedestrianSignalBlocks_0611202
  • R.W. Dunteman Company continues to remove existing pavement along the South leg of Buffalo Grove Road
     

  • Contractor also continues to place temporary asphalt sidewalk along Lake Cook Road
     

  • Trine continues to remove existing storm sewer and install new storm sewer pipe and structures on northbound Route 83 and Lake Cook Road east of Weiland Road
     

  • Areatha to install protective shield at north and south abutments on Buffalo Grove Road bridge to prepare for abutment back wall breaking
     

  • Ruizscape to install temporary fence along the workzone on the north side of the Lake Cook Road construction zone

Thursday, June 11, 2020

TCP_TempStripingLCR_06082020.jpg
  • R.W. Dunteman Company continues to remove the existing pavement along the south leg of Buffalo Grove Road
     

  • Home Towne onsite installing pedestrian push-buttons at the intersection of Weiland Road and Lake Cook Road
     

  • Trine continues to remove existing storm sewer and install new storm sewer pipe and structures on northbound Route 83 and along Lake Cook Road east of Weiland Road

Friday, June 12, 2020

RWD_WeilandRdEmbankmentPrep_06122020.jpg
  • R.W. Dunteman Company to excavate and prepare subgrade along Weiland Road 
     

  • Contractor also hauled out dirt and proof rolled Buffalo Grove Road for subgrade, prepared embankment and placed aggregate sub-base on the Weiland Road Extension
     

  • Trine continues to install new storm sewer pipe and structures along northbound IL-83 and along Lake Cook Road east of Weiland Road

Saturday, June 12, 2020

Pipe icon.png
  • Trine continues to install new storm sewer pipe and structures along northbound IL-83 and along Lake Cook Road east of Weiland Road