CONSTRUCTION UPDATES

WEEK OF JULY 20, 2020

Monday, July 20, 2020

  • R.W. Dunteman Company placed concrete pavement on northbound Buffalo Grove Road south of Lake Cook Road. R.W. Dunteman Company poured concrete pavement patch at the south limit of Buffalo Grove Road. R.W. Dunteman Company removed curb and gutter, sidewalk, and median on along IL-83 north of Lake Cook Road and removed the existing asphalt pavement on IL-83 by Dunkin Donuts.  R.W. Dunteman Company placed aggregate subgrade along Weiland Road

  • Antigo broke the existing pavement along westbound Lake Cook Road from Hastings to Target

  • Quality saw cut pavement and median along Lake Cook Road between Lexington Drive and Hastings Lane  

  • Trine completed a 12” watermain connection along northbound Buffalo Grove Road north of Lake Cook Road and continued the installation of the 6” water main. Trine continued installation of new storm sewer pipe and structures along IL-83

RDW_PCCPourNBBGRdLn2_07202020.jpg

Tuesday, July 21, 2020

  • R.W. Dunteman Company continued to remove the existing pavement on IL-83 north of Lake Cook Road

  • R.W. Dunteman Company continued to grade aggregate subgrade on Weiland Road south of Lake Cook Road and cleaned up from the previous days pavement pour along Buffalo Grove Road

  • Trine continued removing and installing storm sewer pipe and structures along IL-83 south of Lake Cook Road. Trine mobilized equipment and material to Hastings Lane for the proposed storm sewer installations

  • Areatha prepared for retaining wall A piles installation along Weiland Road

Trine_SSRCPInstallationRt83_07212020.jpg

Wednesday, July 22, 2020

  • R.W. Dunteman Company laid out, excavated, and placed aggregate for the sleeper slab on Weiland Road by IL-83

  • R.W. Dunteman Company continued to excavate to subgrade along northbound IL-83 by the Jewel Osco entrance

  • Trine continued to remove and installation of storm sewer pipe and structures along northbound IL-83. Trine started storm sewer work at the east project limit by Hastings Lane

  • Areatha drove piles for retaining wall A along Weiland Road

Trine_SSRCPInstallationLCR_07222020.jpg

Thursday, July 23, 2020

Sanco_TempConcBarrierWallRelocation_0723
  • R.W. Dunteman Company excavated the proposed curb and gutter on northbound IL-83 by Jewel Osco and continued to prepare the subgrade for a proof roll

  • Trine continued to remove and install storm sewer pipe and structures along northbound IL-83 south of Lake Cook Road. Trine started working on storm sewer installations along westbound Lake Cook Road west of Hastings Lane

  • Areatha continued to drive piles for retaining wall A. Areatha framed beams seats at the Buffalo Grove Road Bridge south abutment

  • Sanco installed a temporary concrete barrier wall along westbound Lake Cook Road from Hastings Lane to the Target and Walmart Entrance. Sanco also relocated the temporary concrete barrier on the north side of the Buffalo Grove Road bridge

  • Industrial Fence Inc onsite installing temporary impact attenuators along Lake Cook Road and Buffalo Grove Road

Friday, July 24, 2020

RWD_NBBGRdLn1FineAggregateInstallation_0
  • R.W. Dunteman Company installed aggregate subgrade on IL-83 north of Lake Cook Road

  • R.W. Dunteman Company fine grading aggregate on northbound Buffalo Grove Road from the south limit to the Lou Malnati driveway entrance. R.W. Dunteman Company place topsoil behind the curb and gutter on IL-83

  • Trine continued to remove and install storm sewer pipe and structures along northbound IL-83 south of Lake Cook Road and along westbound Lake Cook Road between Lexington and Hastings

Saturday, July 25, 2020

Trine_SSRCPInstallationLCR_07252020.jpg
  • Trine continued to remove and install storm sewer pipe and structures along northbound IL-83 south of Lake Cook Road and along westbound Lake Cook Road between Lexington and Hastings