top of page

CONSTRUCTION UPDATES

WEEK OF JULY 6, 2020

Monday, July 6, 2020

  • R.W. Dunteman Company places temporary pavement along eastbound and westbound Lake Cook Road and will place Class D patch for the 12” water main crossing at IL-83 and Lake Cook Road

  • R.W. Dunteman Company continues to excavate and haul material for embankment preparation on the Weiland Road extension

  • Home Towne breaks and removes existing street light foundations, traffic signal foundations and hand holes along Lake Cook Road

  • Trine continues to install storm sewer pipe and structures along northbound Buffalo Grove Road and north of Lake Cook Road

TempPavementEB LakeCookRdnearLexington.j

Tuesday, July 7, 2020

  • R.W. Dunteman Company continues to place temporary pavement along eastbound and westbound Lake Cook Road for the upcoming Stage 2B traffic switch

  • R.W. Dunteman Company continues to excavate and haul material for embankment preparation on the Weiland Road extension

  • R.W. Dunteman Company continues to set up a mobile concrete plant off of Aptakisic Road

  • Home Towne continues to break and remove existing street light foundations and hand holes along Lake Cook Road

  • Trine continues to install storm sewer pipe and structures along northbound Buffalo Grove Road north of Lake Cook Road. Contractor continues installing the 12” watermain along Lake Cook Road

Storm%20Sewer%20Installation%20along%20N

Wednesday, July 8, 2020

  • R.W. Dunteman Company completed exploration trench by southbound Lexington Drive for the ComEd utility conflict with the proposed noise wall foundation

  • R.W. Dunteman Company completed undercut excavations on Weiland Road by Route 83 and placed aggregate subgrade

  • R.W. Dunteman Company continues to set up a mobile concrete plant off of Aptakisic Road

  • Trine continue to install storm sewer pipe and structures along northbound Buffalo Grove Road north of Lake Cook Road

  • R.W. Dunteman Company continues installing the 12” watermain along Lake Cook Road

Aggregate%20Subgrade%20Placement%20alon%

Thursday, July 9, 2020

Milling Exisiting Pavement along IL-83.j
  • R.W. Dunteman Company saw cut concrete curb and gutter in the median on Lake Cook Road west of Hastings Lane for the upcoming Stage 2B traffic switch. Contractor continues to set up mobile concrete plant off of Aptakisic Road

  • Home Towne shifted signal heads for the Stage 4 configuration along IL-83

  • Trine continues to install 12” watermain, valve vaults, and valves on westbound Lake Cook Road by Jewel Osco

  • R.W. Dunteman Company continues to install storm sewer pipe and structures along the north leg of Buffalo Grove Road

  • Maintenance Coating Company onsite to switch traffic on IL-83 into Stage 4 configuration

  • Clausen to remove exterior steel diaphragms, install timber blocks and prepare for beam jacking operation at Buffalo Grove Road Bridge

Friday, July 10, 2020

Buffalo%20Grove%20Bridge%20Beam%20Jackin
  • R.W. Dunteman Company milled the median along Lake Cook Road and removed curb for the upcoming Stage 2B traffic switch. Contractor continues to mill in the work zone on IL-83 north of Lake Cook Road

  • Trine continues to install valve vaults and 12" water main along Lake Cook Road

  • Trine removed non special waste material and disposed of contaminated groundwater

  • Clausen onsite to jack existing stage 1 beams and remove the bearings on the north and south abutment of Buffalo Grove Road Bridge

  • Industrial Fence Inc to install impact attenuatores for the IL-83 stage 4 configuration

  • Sanco onsite to install temporary concrete barrier wall for the IL-83 Stage 4 configuration

Saturday, July 11, 2020

Watermain%20Valve%20Installation%20Along
  • Trine continues to install 12" water main along Lake Cook Road and across Lake Cook Road east of IL-83

bottom of page