WEEK OF AUGUST 17, 2020

Monday, August 17, 2020

  • R.W. Dunteman Company poured concrete pavement on Weiland Road by IL-83 for northbound and southbound lanes 1 & 2 and placed asphalt patches, temporary pavement, and sidewalk along Lake Cook Road for the upcoming traffic switch

  • Trine continued the removal and installation of storm sewer pipe and structures along northbound IL-83 and along westbound Lake Cook Road near Lexington Drive

  • Areatha prepared forms for the southeast wing wall and abutment footing on Buffalo Grove Road bridge and continued the removal of the box culvert on Weiland Road

  • Sanco relocated the barrier wall along Lake Cook Road for the Stage 2B traffic switch

  • Industrial Fence Inc. installed impact attenuators along westbound Lake Cook Road for the upcoming Stage 2B traffic switch

RWD_WeilandRdPCCPour_08172020.jpg

Tuesday, August 18, 2020

  • R.W. Dunteman Company graded the aggregate subbase and framed turn lanes on northbound IL-83. R.W. Dunteman Company continued to place asphalt patches along westbound Lake Cook Road for the traffic switch and finished the installation of the cofferdam at Buffalo Grove Creek

  • Traffic Control & Protection placed traffic into the Stage 2B configuration and adjusted signage along the project

  • Trine continued the removal and installation of storm sewer pipe and structures along westbound Lake Cook Road near Lexington Drive

  • Home Towne onsite to relocate two temporary street lighting mast arms and to adjust the traffic signal head for the Stage 2B traffic switch along Lake Cook Road

  • Areatha prepared forms for the southeast wing wall and abutment footing on Buffalo Grove Road bridge and continued the removal of the box culvert on Weiland Road

  • Ruizscape installed inlet filters on existing drainage structures along Lake Cook Road

RWD_WeilandRdTieBarInstallation_08192020

Wednesday, August 19, 2020

  • R.W. Dunteman Company framed, graded and installed dowel baskets and tie bars on turn lanes on southwest Weiland Road south of Lake Cook Road and northbound IL-83 north of Lake Cook Road and milled the median and removed concrete pavement along westbound Lake Cook Road by the project west limit

  • Trine continued the removal and installations of storm sewer pipe and structures along westbound Lake Cook Road near Lexington Drive

  • Areatha poured concrete for the Buffalo Grove Road Bridge south abutment footing and continued to frame the back wall of retaining wall A and removed the wing wall for the existing box culvert

Aretha pouring BG Bridge Footing.jpg

Thursday, August 20, 2020

Areatha Demo Existing Box Culvert.jpg
  • R.W. Dunteman Company removed concrete pavement from westbound Lake Cook Road between Lexington Drive and Hastings Lane. R.W. Dunteman Company explored existing utilities along the Weiland Road extension for the proposed 20” water main installation. R.W. Dunteman Company continued to prepare for upcoming pavement pour on Weiland Road and IL-83

  • Areatha continued work on forming the facing wall for retaining wall A and continued to remove the existing box culvert at Buffalo Grove Creek

  • Trine continued the removal and installations of storm sewer pipe and structures along westbound Lake Cook Road near Lexington Drive

Friday, August 21, 2020

RWD_IL83PCCPour_08212020.jpg
  • R.W. Dunteman Company poured pavement along northbound and southbound Weiland Road near IL-83 and a portion of the turn lane along northbound IL-83. R.W. Dunteman Company continued the removal of the median and pavement along Lake Cook Road from Lexington Drive to Hastings Lane

  • Trine continued the removal and installation of storm sewer pipe and structures along westbound Lake Cook Road near Lexington Drive

  • Industrial Fence Inc. installed impact attenuators along Lake Cook Road to finish the Stage 2B traffic switch

  • Sanco installed a temporary barrier wall along eastbound Lake Cook Road between Raupp Boulevard and the Walmart entrance for the Stage 2B traffic switch

  • Home Towne installed detector loops for the in left-turn lane on northbound IL-83 at the Jewel/Town Center signalized entrance

Saturday August 22, 2020

Trine_SSRCPInstallation_08172020.jpg
  • Trine continued the removal and installations of storm sewer pipe and structures along westbound Lake Cook Road near Lexington Drive

  • Antigo onsite to break the existing pavement along eastbound Lake Cook Road between Buffalo Grove Road and Weiland Road

  • R.W. Dunteman Company onsite to assist Antigo with the pavement breaking layout