CONSTRUCTION UPDATES
SUBSCRIBE TO THE PROJECT E-NEWSLETTER TO RECEIVE CONSTRUCTION UPDATES DIRECTLY TO YOUR INBOX
WEEK OF AUGUST 24, 2020
Monday, August 24, 2020
-
R.W. Dunteman Company excavated the cofferdam and the structure on the northeast corner of Buffalo Grove Road Bridge. R.W. Dunteman Company repaired potholes on eastbound and westbound Lake Cook Road
-
Trine continued the removal and installation of storm sewer pipe and structures along northbound IL-83 south of Lake Cook Road, westbound Lake Cook Road east of Lexington Drive, and northbound Buffalo Grove Road north of Lake Cook Road
-
Areatha dewatered the south abutment and prepared forms for the Buffalo Grove Road Bridge abutment wall pour and continued the removal of wing walls and footings on the existing box culvert
-
Industrial Fence Inc removed existing fence and guardrail along eastbound Lake Cook Road by Buffalo Grove Road
-
AC Iron installed reinforcement bars at the Buffalo Grove Road Bridge south abutment extension

Tuesday, August 25, 2020
-
R.W. Dunteman Company continued to excavate the cofferdam and the structure on the northeast corner of the Buffalo Grove Road Bridge. R.W. Dunteman Company prepared the subgrade along westbound Lake Cook Road between Hastings Lane and Lexington Drive
-
Trine continued the removal and installation of storm sewer pipe and structures along northbound IL-83 south of Lake Cook Road, westbound Lake Cook Road west of Lexington Drive, and northbound Buffalo Grove Road north of Lake Cook Road
-
Areatha continued framing the Buffalo Grove Road Bridge south abutment wall and continued the removal of wing walls and footings on the existing box culvert
-
Industrial Fence Inc removed the temporary attenuator located at the southwest corner of Lake Cook Road and Buffalo Grove Road

Wednesday, August 26, 2020
-
R.W. Dunteman Company prepared the subgrade along westbound Lake Cook Road between Hastings Lane and Lexington Drive and set up a pump to dewater the north abutment cofferdam on Buffalo Grove Road Bridge
-
Trine continued the removal and installation of storm sewer pipe and structures along westbound Lake Cook Road west of Lexington Drive and northbound Buffalo Grove Road north of Lake Cook Road. Trine removed the existing hydrant and valve box at the Jewel and IL-83 intersection
-
Areatha continued framing the Buffalo Grove Road Bridge south abutment wall and set a form for a 56” diameter storm sewer opening
-
Trafic Services Inc removed existing pavement markings and striped new lines along Weiland Road to switch traffic into the Stage 2 configuration

Thursday, August 27, 2020

-
R.W. Dunteman Company started excavating for the Buffalo Creek realignment and continued to prepare subgrade along westbound Lake Cook Road between Hastings Lane and Lexington Drive.
-
Areatha continued to set forms at the Buffalo Grove Road Bridge south abutment wall and wing wall
-
Trine continued the removal and installation of storm sewer pipe and structures along westbound Lake Cook Road west of Lexington Drive and along northbound Buffalo Grove Road north of Lake Cook Road
Friday, August 28, 2020

-
R.W. Dunteman Company continued to place aggregate subgrade between Hastings Lane and Lexington Drive and worked on grading for concrete curb and gutter along northbound IL-83 north of Lake Cook Road, and on southbound and northbound Weiland Road south of Lake Cook Road
-
Trine continued the removal and installation of storm sewer pipe and structures along eastbound Lake Cook Road east of IL-83, westbound Lake Cook Road west of Lexington Drive, and northbound Buffalo Grove Road north of Lake Cook Road
-
Areatha continued framing the Buffalo Grove Road Bridge south abutment wall and wing wall
-
AC Iron installed reinforcement bars at the Buffalo Grove Road Bridge south abutment wall and wing wall
Saturday August 29, 2020

-
Trine continued the removal and installation of storm sewer pipe and structures along eastbound Lake Cook Road east of IL-83 and along westbound Lake Cook Road west of Lexington Drive
-
Areatha continued to set forms at the Buffalo Grove Road Bridge south abutment wall and wing wall