top of page

CONSTRUCTION UPDATES

WEEK OF AUGUST 3, 2020

Monday, August 3, 2020

  • R.W. Dunteman Company graded and framed right turn lanes on northbound Buffalo Grove Road south of Lake Cook Road in preparation for a pavement pour. R.W. Dunteman Company placed aggregate for subgrade and frame on northbound IL-83 north of Lake Cook Road

  • Trine completed 12” and 16” water main connections along Lake Cook Road by Weiland Road and Buffalo Grove Road

  • Areatha continued to install sheet piles for the cofferdam at the north abutment of Buffalo Grove Road Bridge. Areatha finished the removal of concrete at the north abutment backwall and prepared existing rebar for the new beam seat construction

RWD_C&GPour_08032020.jpg

Tuesday, August 4, 2020

  • R.W. Dunteman Company framed, graded and poured pavement at northbound Buffalo Grove Road and Aptakisic Road. R.W. Dunteman Company placed temporary pavement at the driveway entrance of IL-83 and Town Center. R.W. Dunteman Company graded aggregate subgrade on northbound IL-83 and Weiland Road in preparation of the upcoming pavement pours

  • Trine continued with water main connections along Lake Cook Road and finished installation of 12” water main at the southwest corner of IL-83 and Lake Cook Road

  • Areatha continued to install sheet piles for the cofferdam at the north abutment of Buffalo Grove Road Bridge. Aretha installed new rebar for the new beam seats on both abutments and started structure excavation along the northeast corner of the Buffalo Grove Road Bridge

  • Michel installed a dewatering system on northbound Buffalo Grove Road north of Lake Cook Road to assist in the storm sewer installation

Michel_DewateringWellInstallation_080420

Wednesday, August 5, 2020

  • R.W. Dunteman Company poured the right turn lane concrete pavement on northbound Buffalo Grove Road south of Lake Cook Road. R.W. Dunteman Company continued the installation of the cofferdam along Buffalo Creek. R.W. Dunteman Company prepared storm sewer trenches for asphalt pavement patches on northbound IL-83

  • Trine continued with water main connections along Lake Cook Road and continued storm sewer installations and removal along IL-83 south of Lake Cook Road

  • Areatha finished installation of the cofferdam at the north abutment of the Buffalo Grove Road Bridge. Areatha continued formwork for the new beam seats on the north abutment of the Buffalo Grove Road Bridge and continued installing piles for retaining wall A

  • Home Towne installed street lighting conduit under driveways along northbound IL-83 

  • Michel continued installation of the dewatering system on northbound Buffalo Grove Road north of Lake Cook Road to assist in the storm sewer installation

RWD_PCCPourBGRd_08052020.jpg

Thursday, August 6, 2020

RWD_GradeIL83_08062020.jpg
  • R.W. Dunteman Company striped forms from the previous day's pavement pour on Buffalo Grove Road. R.W. Dunteman Company continued to fine grade aggregate subgrade on IL-83 and Weiland Road in preparation for upcoming pavement pours and continued to prepare storm sewer trenches for asphalt pavement patches on northbound IL-83

  • Trine continued removal and installation of storm sewer pipe and structures along Lake Cook Road west of Lexington Drive and continued with water main connections along Lake Cook Road west of Weiland Road

  • Michel continued installation of the dewatering system on northbound Buffalo Grove Road north of Lake Cook Road to assist in the storm sewer installation

  • Areatha broke and removed the concrete retainer column at Buffalo Grove Road Bridge and prepared existing rebar for the new beam seats at the south abutment. Areatha continued to frame for concrete face at retaining wall A

Friday, August 7, 2020

RWD_FrameNBIL83_08072020.jpg
  • R.W. Dunteman Company framed and graded aggregate subgrade for pavement placement on lane 1 and 2 on northbound IL-83 north of Lake Cook Road. R.W. Dunteman Company placed asphalt patch and driveways on northbound IL-83 north of the Jewel and IL-83 intersection  

  • Michel finished installation of the dewatering system on northbound Buffalo Grove Road north of Lake Cook Road to assist in the storm sewer installation and demobilized equipment

  • Trine continued removal and installation of storm sewer pipe and structures along Lake Cook Road west of Lexington Drive and completed the water main connection along Lake Cook Road by the Jewel

Saturday August 8, 2020

Trine_WMConnection_08052020.jpg
  • Trine continued the removal and installation of storm sewer pipe and structures along Lake Cook Road west of Lexington Drive

bottom of page