Monday, August 31, 2020
-
R.W. Dunteman Company removed medians at the intersection of Lexington Drive and Lake Cook Road and at the Walmart Entrance and prepared for temporary pavement placement. R.W. Dunteman Company continued to strip topsoil and excavation soil for the new Buffalo Creek stream alignment
-
Trine continued the removal and installation of storm sewer pipe and structures along eastbound Lake Cook Road east of IL-83, westbound Lake Cook Road west of Lexington Drive, and northbound Buffalo Grove Road north of Lake Cook Road
-
Areatha continued preparing forms for the Buffalo Grove Road Bridge south abutment stem wall pour and continued to work on setting forms for the Retaining Wall A
-
AC Iron tied rebar at Buffalo Grove Road Bridge south abutment and wing wall

Tuesday, September 1, 2020
-
R.W. Dunteman Company placed temporary pavement in the medians at the intersection of Lexington Drive and Lake Cook Road and at the Walmart Entrance. R.W. Dunteman Company continued to strip topsoil along the Buffalo Grove Creek realignment and excavated soil for the new stream bed
-
Trine continued the removal and installation of storm sewer pipe and structures along eastbound Lake Cook Road east of IL-83, westbound Lake Cook Road west of Lexington Drive, and westbound Lake Cook Road west of Buffalo Grove Road
-
Areatha poured the south abutment stem wall from footing to beam seats on Buffalo Grove Road Bridge
-
AC Iron tied rebar for Retaining Wall A

Wednesday, September 2, 2020
-
R.W. Dunteman Company graded and installed tie bars for curb and gutter placement along Buffalo Grove Road and the Weiland Road median by IL-83 and continued to excavate and haul out soil along the Buffalo Creek stream realignment
-
Trine continued the removal and installation of storm sewer pipe and structures along westbound Lake Cook Road west of Buffalo Grove Road and along westbound Lake Cook Road west of Lexington Drive by the Target
-
Areatha continued to frame the south abutment wing wall at the Buffalo Grove Road Bridge

Thursday, September 3, 2020

-
R.W. Dunteman Company poured concrete pavement for the Weiland Road median and the turning lanes along northbound IL-83 north of Lake Cook Road and framed the curb and gutter along IL-83 and Weiland Road. R.W. Dunteman Company continued to excavate and haul out soil along Buffalo Creek stream realignment
-
Trine continued the removal and installation of storm sewer pipes and structures along westbound Lake Cook Road west of Buffalo Grove Road and along westbound Lake Cook Road west of Lexington Drive by the Target
-
Steve Piper removed trees on eastbound Lake Cook Road between Buffalo Grove Road and IL-83 that are in conflict with the construction of Retaining Wall F
Friday, September 4, 2020

-
R.W. Dunteman Company slip formed curb and gutter along northbound Buffalo Grove Road, and hand-poured curb and gutter along the northbound and southbound Weiland Road by IL-83. R.W. Dunteman Company continued to excavate and haul out soil along Buffalo Creek stream realignment
-
Trine continued the removal and installation of storm sewer pipe and structures along westbound Lake Cook Road west of Buffalo Grove Road and along westbound Lake Cook Road west of Lexington Drive by the Target