

CONSTRUCTION UPDATES
WEEK OF SEPTEMBER 14, 2020
Monday September 14, 2020
-
R.W. Dunteman Company excavated, undercut and prepared subgrade along northbound Buffalo Grove Road north of Lake Cook Road and removed existing pavement on northbound IL-83 south of Lake Cook Road
-
Trine continued the removal and installation of storm sewer pipes and structures along eastbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard and installed pipe underdrain on westbound Lake Cook Road between Lexington Drive and the Target
-
Areatha poured the southeast wing wall on Buffalo Grove Road Bridge
-
Home Towne repaired temporary streetlights on Weiland Road, Lake Cook Road and IL- 83

Tuesday, September 15, 2020
-
R.W. Dunteman Company removed existing pavement on northbound IL-83 by the Jewel entrance and installed aggregate subgrade along northbound Buffalo Grove Road by the Walgreens entrance
-
Trine continued the removal and installation of storm sewer pipes and structures along eastbound Lake Cook Road between IL-83 and Raupp Boulevard
-
Areatha set frames for the retaining Wall A facing forms
-
Clausen installed rocker bearings and elastomeric bearings on the existing portion of the Buffalo Grove Road north and south abutment
-
Home Towne adjusted traffic signal heads on IL-83 by the Jewel entrance

Wednesday, September 16, 2020

-
R.W. Dunteman Company removed the driveway entrance and the curb and gutter and placed aggregate subgrade at the NCH immediate care entrance on northbound IL-83 just south of Lake Cook Road. R.W. Dunteman Company also placed aggregate subgrade for the north half of the Jewel driveway entrance along northbound IL-83 by Jewel and along northbound Buffalo Grove Road north of Lake Cook Road
-
Trine continued the removal and installation of storm sewer pipes and structures along eastbound Lake Cook Road between IL-83 and Raupp Boulevard and installed new frames and grates for structures on Weiland Road
-
Areatha framed and poured closure section at Buffalo Grove Road Bridge south abutment and wing wall and continued to prepare forms for retaining Wall A
-
Clausen continued the installation of rocker and elastomeric bearings at Buffalo Grove Road north and south abutment
Thursday, September 17, 2020

-
R.W. Dunteman Company excavated and prepared subgrade along westbound Lake Cook Road from Target to Lexington Road and placed capping stone to finish the aggregate subgrade at the Jewel entrance on northbound IL-83
-
Trine continued the removal and installation of storm sewer pipes and structures along eastbound Lake Cook Road between IL-83 and Raupp Boulevard
-
Areatha excavated the northeast abutment and wing wall extension at the Buffalo Grove Road Bridge
-
Home Towne placed underground conduit for the traffic signal and street lighting at the IL-83 and Jewel intersection
Friday, September 18, 2020

-
R.W. Dunteman Company continued to prepare the subgrade and started the placement of the aggregate subgrade along westbound Lake Cook Road from Target to Lexington Drive
-
Trine continued the removal and installation of storm sewer pipes and structures along eastbound Lake Cook Road between IL-83 and Raupp Boulevard
-
Areatha framed north abutment footing extension at Buffalo Grove Road Bridge
Saturday, September 19, 2020

-
R.W. Dunteman Company continued with the placement of aggregate subgrade along westbound Lake Cook Road between Target and Lexington Drive
-
Trine continued the removal and installation of storm sewer pipes and structures along eastbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard and installed the pipe underdrain on northbound Buffalo Grove Road north of Lake Cook Road