Monday September 28, 2020
-
R.W. Dunteman Company prepared for upcoming pavement pours by placing dowel baskets on northbound Buffalo Grove Road and northbound IL-83 and finished the aggregate subgrade along westbound Lake Cook Road between Lexington Drive and the Target entrance
-
Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between IL-83 and the Target Walmart intersection and installed pipe underdrain along westbound Lake Cook Road by Target and on northbound Buffalo Grove Road north of Lake Cook Road
-
Areatha pumped water out of the north abutment cofferdam at Buffalo Grove Road bridge and removed frame work at retaining Wall A

Tuesday, September 29, 2020
-
R.W. Dunteman Company poured pavement for lanes 1 and 2 on northbound IL-83 south of Lake Cook Road and by the Jewel entrance. R.W. Dunteman Company continued pavement removal and undercut of unsuitable material along eastbound Lake Cook Road from Raupp Boulevard to Buffalo Grove Road
-
Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between IL-83 and the Target and Walmart entrances
-
Home Towne installed traffic signal detector loops at the Lake Cook Road and IL-83 intersection
-
Areatha set forms for the north abutment stem wall on Buffalo Grove Road bridge and removed forms from the retaining Wall A facing wall
-
AC Iron installed rebar for the north abutment stem wall at Buffalo Grove Road bridge
-
Maintenance Coating Co. and Industrial Fence Inc removed a concrete barrier wall and attenuators along westbound Lake Cook Road from Hastings Lane to the Target and Walmart entrances

Wednesday, September 30, 2020

-
R.W. Dunteman Company poured pavement for lanes 1 and 2 on northbound Buffalo Grove Road north of Lake Cook Road and excavated and removed unsuitable material along eastbound Lake Cook Road from Raupp Boulevard to Buffalo Grove Road
-
Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrances. Trine also removed and installed of storm sewer pipes and structures on Weiland Road south of Lake Cook Road
-
Areatha framed the north abutment stem wall at Buffalo Grove Road Bridge
Thursday, October 1, 2020

-
R.W. Dunteman Company prepared and placed the aggregate subgrade along eastbound Lake Cook Road from Raupp Boulevard to Hastings Lane and installed tie bars along IL-83 and northbound Buffalo Grove Road in preparation for curb and gutter placement. R.W. Dunteman Company prepared for upcoming pavement pour by placing dowel baskets along westbound Lake Cook Road from Hastings Lane to the Target and Walmart entrances
-
Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrances and removed and installed the storm sewer pipes and structures on Weiland Road south of Lake Cook Road
-
Areatha framed the north abutment stem wall at Buffalo Grove Road Bridge and set forms for the facing wall on Retaining Wall A
Friday, October 2, 2020

-
R.W. Dunteman Company poured pavement for lanes 2 and 3 along westbound Lake Cook Road from Hastings Lane to Lexington Drive and excavated and prepared and placed aggregate subgrade along eastbound Lake Cook Road from Raupp Boulevard to Buffalo Grove Road
-
Trine removed and installed the storm sewer pipes and structures along eastbound Lake Cook Road between Weiland Road and the Target and Walmart entrances and on Weiland Road south of Lake Cook Road
-
Home Towne installed traffic signal detector loops at the Lake Cook Road and Lexington Drive intersection
-
Areatha poured the north abutment stem wall at Buffalo Grove Road Bridge and poured the remaining portion of the facing wall for retaining Wall A
Saturday, October 3, 2020

-
R.W. Dunteman Company prepared for upcoming pavement pours by placing dowel baskets along westbound Lake Cook Road from Lexington Drive to the Target and Walmart entrances