WEEK OF SEPTEMBER 8, 2020
Tuesday, September 8, 2020
-
Trine continued the removal and installation of storm sewer pipe and structures along eastbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard

Wednesday, September 9, 2020
-
R.W. Dunteman Company removed existing pavement along westbound Lake Cook Road from Lexington Drive to the Target and Walmart entrance and placed a new asphalt driveway at the Jewel entrance on IL-83 and temporary pavement along the median. R.W. Dunteman Company repaired various aggregate entrances and driveways throughout the project due to the previous days rain
-
Trine continued the removal and installation of storm sewer pipe and structures along eastbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard
-
Home Towne covered the detector loop cables in the left turn lane by northbound IL-83 and Jewel entrance intersection

Thursday, September 10, 2020

-
R.W. Dunteman Company removed existing pavement along westbound Lake Cook Road from Lexington Drive to the Target and Walmart entrance and completed general site cleanup on the completed pavement along Weiland Road and IL-83
-
Trine continued the removal and installation of storm sewer pipe and structures along eastbound Lake Cook Road between Buffalo Grove Road and Raupp Boulevard and set frames and grates on storm sewer structures along northbound Buffalo Grove Road, northbound IL-83, and north and southbound Weiland Road
-
Areatha continued framing for the southwest wing wall at Buffalo Grove Road Bridge and removed the forms from the south abutment
-
Quality cut existing pavement along IL-83 by the Jewel entrance and on Lake Cook Road by the Target and Walmart entrance
Friday, September 11, 2020

-
R.W. Dunteman Company excavated to subgrade along northbound Buffalo Grove Road north of Lake Cook Road and on northbound IL-83 south of Lake Cook Road
-
Trine continued the removal and installation of storm sewer pipe and structures along eastbound Lake Cook Road between Buffalo Grove Road and IL-83
Saturday, September 12, 2020

-
Trine installed a restrictor plate in a manhole along westbound Lake Cook Road west of Lexington Drive